3.
In a major setback to OPG Power Gujarat, the National Green Tribunal has directed it to stop work at its 300 Mw thermal power plant at Bhadreshwar, Gujarat. The ongoing construction work was challenged before the Tribunal by fisherfolk, saltpan workers and local villagers. The Tribunal said till all approvals were obtained by the project proponent, no construction activity should take place, said Ritwik Dutta, legal counsel for the appellants.The Tribunal is a specialised body having the expertise to handle environmental disputes involving multi-disciplinary issues. It was established in 2010 under the National Green Tribunal Act for effective and expeditious disposal of cases relating to environmental protection. OPG Power started construc.....