NEEPCO

 

www.neepco.gov.in


Projects
Under operation

Project Location Installed capacity (MW) Fuel Fuel Supply Status Commissioning Date
Kopili Hydro Electric Project Umaronso, North Cachar Hills dist, Assam 275 Hydel - 26/07/2004
Assam Gas Based Power Project Bokuloni Village, Dibrugarh(dist), Assam 291 Natural gas M/S OIL 1.4 MMSCUMD +/- 15% 5/07/1998
Agartala Gas Turbine Power Project Ramchandranagar, Tripura 84 Natural gas - 26/06/1998
Doyang Hydro Electric Project Wokha (dist), Nagaland 75 Hydel - 26/06/2000
Ranganadi Hydro Electric Project Stage I & II Yazali, Arunachal pradesh 405 Hydel - 27/03/2002

 

Under construction/execution

Project Location Installed capacity (MW) Estimated Cost (in Rs crores)
Tuirial Hydro Electric Project Mizoram, Aizawl (Dist) 60 802.79
Kameng Hydro Electric Project West Kameng Dist, Arunachal pradesh 600 2496.90
Pare Hydro Electric Project Papumpare (dist), Arunachal pradesh 110 573.99
Tripura Gas Based Power Project Manarchak, West Tripura dist  101 623.44
 

Proposed

Hydro power projects

S NO Project Location Expected Commissioning Date  Status

1

Ranganadi Hydro Electric Project - Stage II

Arunachal Pradesh

4 years from the date of CCEA clearance

?  DPR submitted was returned by CEA due to high tariff.

?  Updation of DPR held up for want of extension of authorisation/signing of MOA.

?  MOA could not be signed due to issue of payment of upfront premium to the State Govt.

 

2

Mawhu Hydro Electric Project

Meghalaya

In XII th Plan

?  The Govt. of Meghalaya agreed in principle for allotment of the project to NEEPCO.

?  However, signing of MOA is yet to be concluded, which is expected to be signed shortly.

?  Survey & Investigation for preparation of DPR shall be taken up only after signing of MOA.

 

3

 

Kameng-I (Bhareli - I) Hydro Electric Project

Arunachal Pradesh

6 years from the date of CCEA clearance

?  The MOA for execution of the Project was signed with Govt. of Arunachal Pradesh on 21st September, 2006 .

?  Survey & Investigation activities and preparation of DPR could not be taken up due to dominant environmental issues involving Pakke Tiger Reserve.

?  The matter was placed before the EAC, MOE&F, GOI with Terms of Reference and scoping, who recommended obtaining clearance from Standing Council of National Board of Wildlife (NBWL) for the area falling under Pakke Tiger Reserve.

?  The application seeking permission for carrying out survey & investigation was submitted to the Addl. PCCF (WL&BD) & Chief Wildlife Warden, Govt. of Arunachal Pradesh on 20.03.2008.

?  After constant & prolonged persuasions the Addl. PCCF &CWLW vide letter dated 10.09.2009 endorsed the application to the IGF, NBWL, GOI for taking decision as deemed fit.

?  Further, as per the minutes of the second meeting of Inter Ministerial Group held on 7/10/2009 to Guide & Accelerate the development of hydro power of the North East, the Corporation vide its letter dated 30.11.2009 has solicited intervention of the State Government in the matter of obtaining clearance of NBWL & Hon'ble Supreme Court.

?  Keeping in view the difficulties in diverting forest land under Sanctuary for non forest purpose, alternative studies have been carried out to minimize the submergence area and the Govt. of Arunachal Pradesh has been requested vide letter dated 29.12.2009 for advice for development of the project with reduced Installed Capacity to minimize the submergence area or as deemed fit.

 

4

Agartala Gas Turbine Extension Power Plant Tripura

Unit-I: within 26 months from date of investment decision

Unit-II: within 30 months from date of investment decision

-

 

Thermal projects

S NO Project Location  Status Expected Commissioning Date

1

Garo Hills Thermal Power Project, Nangalbibra, Meghalaya

 (500 MW)

Meghalaya

?  Project Area has been identified. Preliminary survey works completed.

?  Empanelment of consultants for preparation of FR/DPR made.

?  Application with requisite fees for coal linkage submitted to the Ministry of Coal in December, 2006.

?  Necessary action has been taken up for formation of a Joint Venture Company, for planning, extract mine and supply the requisite coal to the project.

?  In view of the decision of the Govt. of Meghalaya dated 09.04.2008 regarding non-oprtationalisation of the MoA, all the activities of the project has been held up.

?  Signing of revised MOA is yet to be concluded, which is expected to be signed shortly .

 

36 months from the date of Investment decision.

2

West Khasi Hills Thermal Power Project, Nongstoin, Meghalaya

(240 MW)

Meghalaya

?  The draft MoA was submitted to the Govt. of Meghalaya on July, 2007. Subsequently, proposal for setting up of the project in Joint Venture mode with the State Govt. was submitted on 28.08.08. Clearance from the State Govt. is awaited.

?  Empanelment of consultants for preparation of FR/ DPR has been made.

?  Necessary application with requisite fees was submitted to the Ministry of Coal for Coal Linkage in December, 2006.

32 months from the date of Investment decision.

Financials

Particulars 2008-09(Rs. in Crores) 2007-08(Rs. in Crores)
Gross revenue 971.89 962.68
Sale of power 857.83 860.31
Gross profit 421.21 452.72
Profit available for Appropriation 302.45 285.55

Key points from the directorfs report

 

Profile

Achievements

  • ISO 9001-2000 - QMS

  • SO 14001-2004 - Environmental Safeguards

  • OHSAS 18001-1999 - Occupational Health and Safety Standards

  • MOU Rating - Good

Key Persons

I.P. Barooah, Chairman & MD

Background

The North Eastern Electric Power Corporation (NEEPCO), was incorporated on April 2, 1976 as a wholly owned Government of India Enterprise under the Ministry of Power to plan, promote, investigate, survey, design, construct, generate, operate and maintain hydro and thermal/gas power stations. NEEPCO has the unique distinction of implementing and operating both hydro & thermal power plants from concept to commissioning. It has a record of achievements in successfully completing tasks in the most difficult and complicated of topographical and geological situations demanding the highest levels of knowledge, capability and commitment. To improve the Quality Management System, NEEPCO is already registered as an ISO: 9001-200 Company, NEEPCO has also been accredited with OHSAS 18001 for occupational health and safety risk management system and ISO 14001 for environmental management system.

NEEPCO at a Glance

Year of Establishment

1976

Authorized Share Capital

Rs 35 billion

Installed Capacity

1130 MW

Net worth as on 31st March, 2005

Rs 19.86 billion

Manpower

3238

Employee from NER

90%

Annual Reports

Important Links