Uppur thermal project yet to get off the ground

It is almost a year since former Chief Minister Jayalalithaa laid the foundation stone for the 1,600 MW Uppur supercritical thermal power plant, but the multi-crore project is stuck due to legal wrangles. After Jayalalithaa laid the foundation stone and handed over the broiler turbine generator (BTG) contract to the public sector BHEL, the 󌡐,772 crore project failed to take off following delay in issuing a notification under Section 3 (1) the Tamil Nadu Acquisition of Lands for Industrial Purposes Act, 1997, for acquiring 768 acres of patta lands.After the government finally issued the notification on March 24, the Tamil Nadu Generation and Distribution Corporation (Tangedco) could not alienate the patta lands as a section of the lan.....