First Unit of North India's Inaugural Nuclear Power Plant At Gorakhpur In Haryana To Become Operational By June 2028
The first unit of North India's inaugural nuclear power plant, coming up at Gorakhpur village in Fatehabad district of Haryana, is likely to commence operations in June 2028.The information was given in the meeting presided over by the Chief Secretary, Sanjeev Kaushal regarding the coordination of officers of Haryana Government and Gorakhpur Haryana Anu Vidyut Pariyojana (GHAVP).Providing an update on the project's progress, Project Director, GHAVP, Niranjan Kumar Mittal informed that 74 per cent of the ground improvement work has been completed.Additionally, essential equipment such as end shields and steam generators for the first unit, along with critical reactor components, have been received at the site.Gorakhpur Haryana Anu Vidyut Par.....