Summary

Vindhyachal Super Thermal Power Plant Updated: March 2011 Vindhyachal Super Thermal Power Plant Promoter NTPC Location Sidhi, Madhya Pradesh Installed capacity 2260 MW  (Approved: 3260 MW) Unit configuration Stage I: 6 x 210 MW  Stage II: 2 x 500 MW  Stage III: 2 x 500 MW Stage IV: 2 x 500 MW Estimated cost Stage I & II- INR 4053.42 Crore + Stage-III  - INR 4201.5 Crore Latest Approved Cost/Date: INR 1460.37 Crore/November 1990 [Stage I] INR 2593.05 Crore/November 2001 [Stage II] Land Availability Available Power Purchase Agreement Madhya Pradesh, C......