Summary

Updated: June 2011  Balagarh TPP             Promoters Balagarh Power Company Limited (promoted by CESC  ) Location Balagarh Installed Capacity 500 MW Estimated Cost INR 2234 Crore Type of Fuel Coal PPA Initialed on March 6, 1995. Not yet signed. TEC August 16, 1995 EPC Hanjung, Korea O&M CESCON Limited Investment till date INR 49 Crore Foreign Investment Approval Automatic approval (foreign equity < 74%) Environment Clearance March 20, 1995 Fuel Linkage......