The Dhauliganga HEP (280 MW) was sanctioned in April, 1991 for implementation by NHPC in the Central Sector at an estimated completion cost of INR 601.98 Crore (including IDC of INR 84.53 Crore). The project was scheduled to be completed within a period of seven and a half years from the date of sanction. The Revised Cost Estimate of the project was approved in July, 2000 at a cost of INR 1578.31 Crore (including IDC and financing charges of INR146.87 Crore at August 1999 PL). As per the RCE, the project is scheduled for completion in March 2005. The project is a run of the river scheme located on river Dhauliganga, a tributary of river Sarda, in Pithoragarh Distt. of Uttranchal.......