DetailedNewsletter   Wednesday, April 29, 2009



Infraline Comprehensive Detailed Newsletter

  
 
Power (15 items)

 Oil and Gas (17 items)

   
Coal(2 items)

 Telecom (7 items)

Transport (5 items)

PXIL

POWER EXCHANGE INDIA LIMITED

Highest Traded PriceRs 13.50 / unit
Average Traded PriceRs 12.31 / unit
Lowest Traded PriceRs 11.00 / unit
Traded volume for the day0.250 MUs
Total Sell Bids0.950 MUs
Total Buy Bids 0.300 MUs

CONTACTS: WWW.POWEREXINDIA.COM,+91-22-26598514/15




  
>> | Power ( 15 News Items)

General

Not enough balance-of-plant manufacturers, says Bhel - Express serious concern over limited number and capability of construction contractors
Infraline.com
  • Bharat Heavy Electricals Ltd has expressed serious concern over the limited number and capability of construction contractors on one hand and vendors of balance-of-plant material on the other. According to the public sector major, the capabilities of manufacturers for both standard and supercritical units as well as other main plant package materials were in sync with the planned capacity addition, but delays in acquiring BoP material and issues regarding construction contracts were a menace to the timely completion of power projects.

  • Bhel officials, at a recent meeting with the ministry of power, said that India had limited number and capability of construction contractors as well as vendors of balance-of-plant materials such as coal and ash handling systems, water treatment plants, cooling water systems, air-conditioning and ventilation systems, fire protection systems, cooling towers, construction equipment, and civil works and services.

  • The equipment manufacturer stated that it was necessary to encourage indigenous industry to set up capacity for key inputs like high-grade CRGO steel for generators and transformers, critical casting and forgings for turbines generators, boiler quality plates, and special quality piping material as most of these items were currently being imported. There was a need to develop new qualified erection and commissioning agencies and contractors to take up civil, mechanical and electrical works in the construction of large power plants, they felt.

  • Existing players also needed to be encouraged to augment and build up capacities. Standardisation of unit ratings, layouts and specifications for thermal plants would enable batch production of equipment and these can be tied up with various equipment vendors, the officials said, adding that the vendor base in each area should be enlarged.

Source

[Top]
CII-Kerala hails withdrawal of 20 per cent power restriction by Kerala Electricity Regulatory Commission on HT-EHT and LT consumers
Infraline.com
  • The CII Kerala Chairman, Mr Sanjaya Mariwala, has welcomed the withdrawal of 20 per cent power restriction by the Kerala State Electricity Regulatory Commission on HT-EHT and LT consumers of KSEB. He said that CII has been demanding for withdrawal of the power restriction and it is a great relief for industry in the State which is reeling under the pressure of economic slowdown.

Source

[Top]
AP industries to face less power cuts - Power holiday for high tension industrial consumers to be brought down to about one day a week
  • The power holiday for high tension industrial consumers in Andhra Pradesh will be brought down to about one day a week from three days and the domestic sector will not have any load shedding henceforth. The power situation has partly eased with gas-based independent power producers (IPPs) commencing generation from the gas supplied by GAIL through East-West pipeline of Reliance Industries Ltd. 

  • The unrestricted energy demand has been reduced from 230 million units a day to 205 mu, as against average demand of about 221 mu from the first week of April 2009. Therefore, the State continues to meet the gap of about 15 mu by power purchase from central generating stations.

  • According to a statement from the Chief Minister’s Office on Tuesday (April 28), while GAIL has stepped up gas supplies, all the power projects in the State will get gas from the Krishna-Godavari basin next month and this will pave way for additional capacity. In addition to generating power from various gas-based projects in the State, initially from re-gassified liquefied natural gas (RLNG) supplied by GAIL, and thereafter from LNG from the KG basin, the Generation Corporation of Andhra Pradesh (AP Genco) will add another 300-MW unit of Vijayawada Thermal Power Station in the first week of May.In the meantime, the Chief Minister, Dr Y.S. Rajasekhara Reddy, has directed that the farm sector continue to get assured supply of seven hours till all their requirements are met. According to estimates, the rabi season will come to end by mid-May. The base availability of power is estimated at 165 mu and this has increased to about 184 mu, with IPPs generating an additional 750 MW using RLNG. According to supply data, AP Transco is supplying 191 mu with a peak demand of 8,430 mw and purchase of 18 mu. The load relief for the industrial consumers is about 15 mu.

Source

[Top]
Mr RS Mina takes over as Director (Personnel) of NHPC Limited
Infraline.com
  • Mr RS Mina has taken over as Director (Personnel) of NHPC Limited. Prior to this, he was Executive Director (Consultancy & Business Development) in NHPC. Born in 1957, Mina did his Bachelors degree in Electrical Engineering in 1979. He also holds MBA degree with specialisation in Financial Management and Human Resource Development. He started his professional career as Engineer Trainee in Indian Petro Chemical Corporation Ltd. in 1980. His carrier with NHPC began in 1981 as Engineer (Electrical). 

Source

[Top]

Projects/Project Finance

ABB India wins substation orders worth Rs 4.25 billion from PowerGrid Corporation to boost capacity and help improve grid reliability
Infraline.com
  • ABB India, a power and automation technology group, has won substation orders worth Rs 425 crore from Powergrid, India’s national transmission utility, to boost capacity and help improve grid reliability. The orders were booked in the first quarter. According to a statement from ABB, it is responsible for the design, supply, installation and commissioning of 765/400 kilovolt (kV) substations at Agra (Uttar Pradesh), Wardha (Maharashtra), Bilaspur and Seoni (Madhya Pradesh), and of a 400/220 kV substation at Palakkad (Kerala). The projects are expected to be completed by mid-2011.“We are pleased to be a part of Powergrid’s efforts to strengthen India’s power infrastructure,” said Biplab Majumder, vice-chairman and managing director, ABB India. “These substations for the national grid are an integral part of the country’s plans to develop an ultrahigh-voltage transmission network, improving transmission efficiency and addressing growing demand for electricity.” The equipment to be supplied includes a range of circuit breakers; current transformers and capacitor voltage transformers, used for monitoring current and operations; surge arrestors; protection systems; control and relay panels; as well as the substation automation.The substation projects are part of Powergrid’s program to strengthen the national transmission grid and to enhance the inter-regional power transfer capacity to around 37,000 megawatts by 2012. An extensive 800kV and 1,200kV ultrahigh-voltage system is expected to form the backbone of the transmission network and facilitate the transfer of power across India.

Source

[Top]
Larsen & Toubro plans to foray into power generation - Company is eyeing strategic stakes of up to 26 per cent in private power projects
Infraline.com
  • Larsen & Toubro, India's top infrastructure and construction firm, may have burnt its fingers by trying to acquire the fraud hit Satyam Computer Services but this has not dampened its plans to diversify. The company has firmed up its decision for backward integration and is now planning to generate electricity instead of being a mere power project equipment supplier. An exhaustive blueprint is already in place for this purpose. 

  • The company is eyeing strategic stakes of up to 26 per cent in private power projects. It may also set up plants with a capacity of 660 megawatts preferably coal-based with an initial investment of Rs 1200 crore. In a nervous business environment, analysts say will only help L&T to gain an entry as most of the independent power players are desperate for funds.

  • But generation is not at the cost of the existing power engineering and contracting work. Most of its bulk orders are tied up with the government agencies and its supercritical manufacturing capabilities, key for the UMPPS, will be ready in two years time. L&T, till now was only making machinery that would generate power but now it wants to be a direct participant in India growth story by producing electricity in India. But it remains to be seen whether this backward integration be successful or backfires the Satyam way.

Source

[Top]
NHPC to set up 100 MW wind project in MP - Also plans to enter into solar as well as other non-conventional sources of energy generation
Infraline.com
  • The country's largest hydro-electric power producer, NHPC, is foraying into wind power generation by setting up a 100-MW power project in Madhya Pradesh. "The company is setting up a 100-MW wind energy project at Kukroo in Madhya Pradesh," NHPC CMD S K Garg said. It also plans to enter into solar as well as other non-conventional sources of energy generation.

  • "We have received approval from the Madhya Pradesh Energy Development Corporation (MPEDC). NHPC is entering into wind power generation through its subsidiary Narmada Hydro-electric Development Corporation (NHDC)," he said. NHDC is a joint venture between NHPC and the Madhya Pradesh government, where NHPC holds 51% stake and the rest is held by the state government. The Centre for Wind Power Technology (CWPT), under the Ministry of New and Renewable Energy (MNRE), had invited proposals for establishing wind energy project in Madhya Pradesh.

  • On being asked about the investments in the area of wind energy generation, NHPC Director (Finance) ABL Srivastava said, "This is (wind power project) in its initial stage therefore the investment has not been decided yet." Garg said, apart from wind energy, the company plans to enter other forms of energy generation -- solar, non-conventional sources etc. Besides, NHPC is also developing a 1,000-MW thermal power project at Khandwa in Madhya Pradesh through NHDC. The company is also working at making all its projects environment-friendly.

Source

[Top]
National Thermal Power Corp expects to start coal mining from its huge Pakri Barwadih block in Jharkhand in the second half of 2008-09
Infraline.com
  • Ending delays in its captive mining effort, NTPC Ltd expects to start coal mining from its huge Pakri Barwadih block in Jharkhand in the second half of 2008-09. The block was awarded to the power utility in October 2004 but several impediments related to land acquisition, forest clearance and mining operatorship resulted in a delay of at least two years in the production schedule.

  • Located in the prolific North Karanpura coalfields of Jharkhand, the PB block has estimated reserves of 1.6 billion tonnes out of which at least 700 million tonnes are mineable. Once production starts from the PB block, it would be NTPC's first step in achieving coal security. NTPC is estimated to invest around Rs 1,800 crore to bring to the PB block to production. At peak production, the block could yield 15 million tpa, although production would begin at lower levels, NTPC officials said.

  • As far as domestic reserves are concerned, NTPC has been alloted eight coal blocks with aggregate reserves of nearly 6 billion tonnes, spread over Jharkhand and Orissa (see table). Two of these-Brahmani and Chichro-Patsinal, both in Orissa-would be operated in equal partnership with Coal India Ltd. The Brahmani block is said to hold 1.9 billion tonnes of coal.

  • NTPC is also pursuing coal block acquisition in Indonesia and Mozambique, and is also part of a multi-partite special purpose vehicle “International Coal Ventures Ltd” to explore coal mining opportunities in Australia, Indonesia etc. By 2012, NTPC is expected to annually need around 225 million tonnes of coal against 130.71 million tonnes consumed in 2008-09. According to industry norms, 1 million tonnes of coal is needed to run coal-fired power capacity of 200 mw for a year.

  • By this standard, NTPC's projected coal requirement stands for 45,000 mw of coal-fired capacity. NTPC has projected to add a total power capacity (including that owned in joint venture) of 22,430 mw during the 11th Plan period (April 2007 to March 2012). Out of this, 2,740 mw was commissioned in the first two years of the Plan period, while another 3,300 mw is scheduled to commission this fiscal, 2009-10. NTPC recently crossed the 30,144 mw installed capacity mark, including 2,294 mw coming from joint venture projects (this includes gas-fired capacity).

  • By 2012, NTPC would have over 50,000 mw of power capacity—mainly coal but also including hydropower and renewable energy. Currently, domestic coal (sourced from Coal India Ltd) meets 95 per cent of NTPC's requirement of coal-fired plants, while the rest is imported. In 2011-12, NTPC expects that captive coal production would be 15 million tonnes, mainly coming from the PB block.

  • NTPC also expects to import 15 million tonnes, while Coal India and its subsidiaries would supply the bulk-195 million tonnes. It is also learnt that the mining plans for two more coal blocks have been approved by the coal ministry. These mines-Chatti Bariatu and Kerandari-are expected to together yield 13 million tonnes of coal per year. As an industry thumb rule, coal production from alloted blocks is expected to have a gestation period of 72 months, including 27 months for preparation of the geological reserve report, which is applicable in the case of unexplored or partially-explored blocks.

Source

[Top]
Work on phase-I of Meenakshi Group's 540 MW coal-based power project at Krishnapatnam in Nellore district of Andhra Pradesh under way
  • Work on phase-I of the Meenakshi Group's 540-mw coal-based power project at Krishnapatnam at Thammenapatnam village, Chillukar, in Nellore district of Andhra Pradesh, is under way. Company officials said that the project was being set up in two phases, each having a capacity of 2x135 mw. The power plant, spread over 225 hectares, entails an investment of around Rs 3,000 crore. Meenakshi was in the process of achieving financial closure for the project which will have a debt equity ratio of 75:25. Development Consultants Pvt. Ltd has been appointed as consultant for the project.

  • Around 0.86 million tpa of imported coal will be required for phase-I, which is slated for commissioning in February 2012. Work on phase-II is likely to begin by October 2009 with completion scheduled for August 2010. Meanwhile, Meenakshi Power, a subsidiary of Meenakshi Group, has commissioned its 25-mw Middle Kolab hydropower project in Koraput district of Orissa.

Source

[Top]
Orissa: Electrification of additional 4000 villages in the state under RGGVY in advance stages - Likely to be completed by June this year
Infraline.com
  • Electrification of additional 4000 villages in the state under the Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) are in advance stages and is likely to be completed by June this year. The progress of rural electrification in Orissa had suffered due to unavailability of adequate poles. But due to proactive steps taken by the state government, the Central Public Sector Undertakings (CPSUs), entrusted with the task of rural electrification, have dumped poles in the villages to be electrified during the last two months.

  • Sources said, about 2600 poles have been erected in these villages during this period. This has expedited the electrification work in the villages which are covered under the RGGVY during the 11th five year plan period. The state government is pressing the 3 CPSUs, National Hydro-Power Corporation (NHPC), National Thermal Power Corporation (NTPC) and Power Grid Corporation of India Ltd. (PGCIL), to complete the electrification of these villages by June 2009, sources said. 

  • Though the central PSUs reported electrification of about 5000 villages and habitations in the state under the scheme, the state government has sought the details of the villages and habitations electrified. Sources said, parallel physical work was started along with the survey and other preliminary work which has expedited the implementation process. As per the guidelines of the RGGVY, the physical work of the projects normally starts by May.

  • On the otherhand, the progress of rural electrification work in Angul and Nayagarh district is not satisfactory. NTPC, the central PSU entrusted with the work in both the districts had assured the state government to complete the work by May this year. However, given the slow pace of work, the deadline is unlikely to be met. Slow pace of the rural electrification work in these districts is attributed to the non-deployment of adequate manpower by the implementing agency. Though all the materials for erection were available, the work couldn’t proceed due to the non-availability of labour, sources added.

Source

[Top]
Alstom awarded a contract for 1 bn pounds by RWE for design and construction of a full turnkey, gas-fired combined-cycle power plant in Wales
Infraline.com
  • Alstom has been awarded a contract worth approximately 1 billion pounds by RWE power plc for the design and construction of a full turnkey, gas-fired combined-cycle power plant in Pembrokeshire, Wales. With an output of approximately 2,000 MW, the new plant will be the biggest and one of the most efficient of its kind in the UK, capable of supplying power to around three million homes. 

  • The new plant will be built on the site of the previous oil-fired power station. It will include five Alstom GT26 turbines and accompanying core components supplied by Alstom. It will offer high load flexibility while maintaining low emissions and high efficiency. The plant will be able to be run as efficiently at low load as at full capacity during peak hours, allowing the operator to respond to fluctuating energy demands. It will be among the most efficient of its kind. 

  • Approximately 40 per cent of the UK energy fleet was built before 1975 and will need replacement in the short to medium term. The Pembroke power plant is part of RWE npower’s plan to renew its power generation fleet with new, more efficient and more environmentally friendly power plants. “This new project clearly demonstrates that Alstom’s engineering expertise is crucial to the power industry in the UK, and around the world. This is the second contract signed by Alstom with RWE npower in less than 2 years, which underlines our customer’s confidence in our engineering ability,” said Philippe Joubert, President of Alstom Power. This project is the second one that Alstom has signed with RWE npower in the UK, following the contract won in 2007 for the gas-fired 1,650 MW Staythorpe power plant, currently under construction in Nottinghamshire. In addition to the Staythorpe power plant, Alstom is also building in the UK the Centrica’s Langage and E.On’s Grain power plants. Including the Pembroke plant, these four power plants will add close to 6 GW of new electrical power to the UK grid.

Source

[Top]

Fuel Issues

Reliance Industries inks gas supply agreements from KG-D6 fields with power firms including Essar Power and an Anil Ambani Group firm
Infraline.com
  • Reliance Industries has inked deals to supply gas from its eastern offshore KG-D6 fields to most power sector consumers, including Essar Power and an Anil Ambani Group firm. However, it is yet to sign the Gas Supply and Purchase Agreement (GPSA) with state-run NTPC Ltd and Ratnagiri Gas and Power, the owner of the Dabhol power plant. NTPC is to get 2.67 million cubic metres per day of gas from KG-D6 while Dabhol has been al located 2.7 mmcmd.

  • Ratnagiri Gas and Power cannot immediately take KG-D6 gas and so it has not signed the GSPA, which has provisions of take-or-pay,'' a Government official said. "In the case of NTPC, RIL has sent a draft GSPA and the agreement is likely to be signed soon. ''

  • The power sector had been allocated 18 mmcmd gas out of the initial 40 mmcmd volumes from KG-D6. Gas of 6.22 mmcmd would go to eight power plants in Andhra Pradesh, the landfall point of the gas from the Bay of Bengal fields. Essar's 300 MW power plant in Gujarat will get 1.08 mmcmd while ADAG's 220-MW Samalkot plant in Andhra Pradesh will get 0.19 mmcmd. Gas will be sold at government-approved rates of USD 4.20 per million British thermal unit plus taxes and transportation, the official said. Company officials could not be reached for comments.

Source

What Went Before ...
Essar Power requests for supply of D6 gas at Hazira instead of Vapi : 4/29/2009
RIL to sell natural gas from its eastern offshore KG-D6 fields to Anil Ambani Group firm's power plant in AP at government approved rates : 4/25/2009
Gas-based IPPs get into production mode - All power plants, with capacity of about 1,800 MW, will get gas supplies from KG basin by May : 4/23/2009
GVK commissions 220 MW Jegurupadu second phase power plant using gas supplied by GAIL through a swap deal with Reliance Industries : 4/16/2009
Fast Rewind >>
[Top]
Long-term FSA between Coal India and power utilities led by navratna firm NTPC set to miss April-30 deadline on account of procedural delays
Infraline.com
  • The long-term fuel supply pact between the country's largest coal producer, Coal India, and power utilities led by navratna firm NTPC is set to miss the April-30 deadline on account of procedural delays. In a meeting between Coal India Ltd (CIL) and NTPC officials last evening, the draft of Fuel Supply Agreement (FSA) was fine-tuned and would now be sent to the boards of the two companies for approval, an official said.

  • The process of signing the FSA is likely to be completed in a month's time, he said, adding the pact between the two companies would act as a benchmark for other units to follow. When contacted, Coal India Chairman, Mr Partha S Bhattacharyya said, "All the issues (pertaining to the FSA) between both the parties have been worked out and the pact is likely to be signed around May 20.'' Earlier, CIL had set April 30 as the deadline for 72 power utilities, including NTPC, to conclude the FSA, which is a long-term supply-pact between the coal producer and consumers.

  • The pact has, however, been delayed by almost a year now due to differences over fixing of a "trigger level'', the minimum assured level of coal supply and offtakes, failing which both parties attract penalty. After a series of meetings between CIL and NTPC, the trigger level has been agreed at 90 per cent of the assured supply of 307 million tonnes (MT) to the power units, which have come up before March 31, 2009.

Source

What Went Before ...
Interview: 'NTPC to become a 75,000-mw company by 2017' - CMD talks about the company's strategy for capacity addition and new ventures : 4/23/2009
Coal India-NTPC to enter into fuel supply pact by the end of this month - Issues pertaining to the Fuel Supply Agreement has been resolved : 4/22/2009
Draft Coal Import Policy for procurement of imported coal for NTPC Stations : 4/20/2009
NTPC plans to acquire coal blocks in Indonesia and Mozambique later this year to raise its generation capacity by 22,430MW in three years : 4/9/2009
Fast Rewind >>
[Top]
Essar Power requests for supply of D6 gas at Hazira instead of Vapi
[Source : Infraline News Team]
Infraline.com
  • Essar Power has requested MoP&NG to direct RIL to supply 1.08 MMSCMD of D6 gas at Hazira instead of Vapi.  In the case of GTA, RIL has stipulated that the gas will be made available at Vapi from where Essar will have to make arrangement with GSPL for transmission of gas from Vapi to its Power Plant at Hazira. For this, Hazira will have to enter into a Transmission agreement with GSPL which insists on entering into a long term Ship or Pay Transmission agreement.

  • As per the GSPA with Reliance, there is no binding obligation on Reliance for supply of the gas as there are no such provisions in the proposed agreement. As per the agreement, Reliance can stop gas supplies with a maximum liability of 30 days. In view of this, Essar now finds it extremely difficult to enter into Ship or Pay long term transmission agreement with GSPL.

  • Essar has now requested MoP&NG to direct RIL to deliver the gas to Essar at Hazira has RGTIL has extended its East West pipeline to Hazira and has setup a gas receiving station from where Essar can carry the gas through its pipeline to its Power Plant at Hazira.

Source : Infraline News Team

[Top]
Ministry issues final list for Power Customer eligible to receive D6 gas till September 2009
[Source : Infraline News Team]

Ministry has issued the final list for Power Customer eligible to receive D6 gas till September 2009 in accordance with the approved guidelines for sale of natural gas. While issuing this list, MoP&NG has observed that due to capacity constraint on Gas Rehabilitation Expansion Programme (GREP), the gas earmarked for NTPC at Faridabad and Dadri in the list detailed below should be supplied to other plants of NTPC, till GREP expansion is completed. Directions regarding the same would be issued separately.

Further, MoP&NG has observed that the supply of D6 gas to inter-alia NTPC's existing gas based plants in the list should be made at the price earlier approved by EGOM.

Name of Power Station Gas Allocation from D6 field
Kondapalli 0.27
Jeguurpadu CCGT (GVK) 0.15
Jeguurupadu CCGT (GVK) Ext. 0.82
Samlkot CCPP / Paddapuram 0.19
Vemagiri CCPP 1.38
Gautami CCPP 1.73
Konaseema CCPP 1.66
Faridabad CCGT 0.13
Anta CCGT 0.13
Dadri CCGT 0.45
Kawas CCGT 1.76
Gandhar CCGT 0.30
Dhuvaran CCPP (GSEL) Extn. 0.36
Uran CCGT 0.32
Vatwa CCGT (Torrent Power) 0.32
GPEC - Paguthan CCGT 0.97
GIPCL - Stage II CCGT 0.01
Essar IIMP CCGT 1.08
Sugen Torrent 2.74
Total 15.28

Source : Infraline News Team

[Top]

What's New in Power Sector Database http://Power.Infraline.com
 
Regionwise, Sectorwise & Utilitywise List of H.E. Stations with Capacity above 3 MW (March 2009)
.
Statewise Status of Hydro Electric Potential Development as per Installed Capacity (March 09)
.
Monthly Progress Report of Construction of Transmission Works (March 2009)
.
Status of Sanctioned Ongoing & Under Execution Hydro Projects (April 2009)
.
Hydro Capacity added during 11th Plan (2007-12) (March 09)
.
Updated status of Torrent Power's Sugen CCPP as on March 2009

FSA for supply of gas for 2 Blocks has been executed with IOC in Jan.06 and for 3rd Block is under finalization. Gas Transmission Agreement (GTA) for laying gas pipeline has been executed with Gujarat State Petronet Limited (GSPL).

.
Profile & updated status of NDPLS's 108 MW Rithala CCPP

North Delhi Power Limited (NDPL) is setting up a 108 MW natural gas based combined cycle power plant (CCPP) to meet the additional requirements of power crunch for the city of Delhi. The power plant is needed due to the present scenario of power deficit in the State as well as in the Northern Region. The plant is proposed to be located at Sector 11, Rohini, District North-West in Delhi having co-ordinates 28° 41’ N Latitude and 77° 06’ E Longitude. The power generation shall be through gas based Combined Cycle Power Plant (CCPP) of European manufacture.The estimated project cost is Rs. 256.48 Crores.

.
R V Shahi's Weekly Column for Infraline - Decentralised Distributed Generation: A pragmatic part solution to power shortages (April 27, 2009)
.
CEA's Report on Renovation, Modernisation & Uprating of Hydro Projects (March 2009)
.
CERC - Tariff Order for FY 2009-10 (April 20-21, 2009)
The Following Orders have been released by CERC
  • Determination of provisional transmission tariff for 2nd 400/220 kV, 315 MVA Auto transformer and 2nd 400 kV, 63 MVAR Bus Reactor at Tiruneveli sub-station along with associated bays and equipment under transmission system associated with Kudankulam Atmoic Power Project (2x1000MW) from the date of commercial operation to 31.3.2009 in Southern Region. Power Grid Corporation of India Ltd, Gurgaon
  • Determination of final transmission tariff and additional capitalization from the date of commercial operation to 31.3.2008 for (i) LILO of one Ckt. of 400 kV D/C Ballabgarh-Dadri transmission line at Maharanibagh GIS along with associated bays and 315 MVA 400/220/33 kV ICT-I at Maharanibagh GIS along with associated bays (ii) 315 MVA 400/220/33 kV ICT-II at Maharanibagh GIS along with associated bays under Tala HEP, East-North Inter-connector and Northern Region Transmission System for period up to 2009. Power Grid Corporation of India Limited, Gurgaon (iii)
  • Determination of final transmission tariff up to the date of commercial operation and additional capitalization from the date of commercial operation to 31.3.2008 for (i) LILO of 400 kV Satna-Bina Ckt-I at Bina (Power Grid) along with associated bays (ii) Circuit # IV & III of 400 kV D/C Satna-Bina transmission line (iii) LILO of Raipur-Rourkela D/C line at Raigarh and Raigarh sub-station with one ICT & 315 MVA 400/220 kV ICT-II at Raigarh sub-station under Vindhyachal Stage-III transmission system in Western Region for the period up to 2009. Power Grid Corporation of India Limited, Gurgaon (ii)
  • Determination of final transmission tariff up to the date of commercial operation and additional capitalization from the date of commercial operation to 31.3.2008 for (i) 50 MVAR Bus Reactor at Hissar sub-station, (ii) LILO of 400 KV Moga- Hissar line, ICT-I at Fatehabad sub-station, 4 nos 220 kV line bays (feeders from Fatehabad-1 and Fatehabad-2) and 50 MVAR Bus Reactor bay along with associated bays at Fatehabad sub-station. (iii) 315 MVA, 400/220 kV ICT-II along with associated bays at 400/220 kV Fatehabad sub-station under Northern Region System Strengthening Scheme- III in Northern Region for tariff block 2004-09 period. Power Grid Corporation of India Limited, Gurgaons
.
CERC - General Order for FY 2009-10 (April 15 to 22, 2009)
The Following Orders have been released by CERC
  • Downgrading of inter-State trading licence from Category `F` to Category `III`. Ispat Energy Limited
  • Downgrading of inter-State trading licence from Category `F` to Category `III`. Kalyani Power Development Pvt. Limited, Pune
.
Concept paper on new power allocation guidelines beyond 2011
.
Profile and updated status of Athena's Demwe Lower HEP in Arunachal Pradesh

The ADPPL is a Special Purpose Vehicle (SPV) formed by Athena Energy Ventures Pvt. Ltd. (AEVPL) for implementation of the 1630 MW Demwe Lower HEP. ADPPL has invited Expression of Interest through Global/ International Competitive Bidding (ICB) for the execution of the project.

.
Highlights of NHPC's Projects during March 2009
.
Statewise, Sectorwise Installed and Capacity Addition Target & Achievement during X & XI Plan (March 2009)
.
PGCIL's Presentation on Transmission System associated with Tilaiya UMPP (4000 MW) [March 2009]
.
Generation from NTPC's power stations during March 2009
.
Status of NTPC's New Projects (March 2009)
.
Monthly Flash Report of NTPC's Projects (March 2009)

The above document contains the detailed status of following NTPC's projects:

S.No Project Capacity/Units 

1.

Kahalgaon STPP Stage-ll (Phase-ll )

1X500 MW (Unit#7)

2.

Sipat STPP Stage-I

3x660 MW (Unit#1, #2, #3)

3.

Barh STPP Stage-I

3x660 MW (Unit#1, #2, #3)

4.

Korba STPP  Stage-lll

1x500 MW (Unit#7)

5.

Farakka STPP Stage-Ill

1x500 MW (Unit#6)

6.

Dadri STPP Stage-ll

2x490 MW (Unit#5, #6)

7.

Simhadri STPP Stage-ll

2x500 MW (Unit#3, #4)

8. Bongaigaon TPP 3x250 MW (unit#1, #2, #3)

9.

Barh STPP Stage-ll

2x660 MW (Unit#4, #5)

10.

Mouda STPP

2x500 MW (Unit#1, #2)

11.

Koldam Hydro Electric Power Project

4X200 MW (Unit#1, #2, #3, #4)

12.

Loharinag Pala HEPF

4x150 MW (Unit#1, #2, #3, 4)

13.

Tapovan Vishnugad HEPP

4x130 MW (Unit#1, #2, #3, #4)

.
Appellate Tribunal For Electricity (Judgements 2009-10)

Following Judgements Released in April 2009

  • Maharashtra State Electricity Board & Anr.
    Versus
    Maharashtra Electricity Regulatory Commission

  • M/s G.V.K. Power (Goindwal Sahib) Ltd.
    Versus
    Punjab State Electricity Regulatory Commission
    & Others

  • Tamil Nadu Electricity Board
    Versus
    Tamil Nadu Electricity Regulatory Commission
    & Others

.
Invitation for Infraline's Monthly RTC on the topic 'Decentralized Distributed Generation' to be held on May 6, 2009)
.
TNERC - Tariff Order for FY 2009-10 (April 01 to 09, 2009)

The Following Orders have been released by TNERC:

  • Interest on Security Deposit from consumers
  • Orders on petition filed by M/s  Kaveri Gas Power Ltd

  • Orders on petition filed by M/s Arkay Energy (Rameswaram) Limited
.
TNERC - General Orders for FY 2008-09 (February 12 to 25, 2009)

The Following Orders have been released by TNERC:

  • Orders on petition filed by M/s  Arasan Syntex Limited
  • Orders on petition filed by M/s  Caltex Gas India Private Limited (ii)
  • Orders on petition filed by M/s   The Secretary,Tamil Nadu Electricity Board (iii)
  • Orders on petition filed by M/s   PPN Power Generating Company Pvt.,Ltd(iv)
  • Orders on petition filed by M/s  Apollo Infrastructure Projects Finance(v)
  • Orders on petition filed by M/s Pandian Chemicals Limited (vi)
  • Orders on petition filed by M/s SRM Energy Private Limited (vii)
  • Orders on petition filed by M/s Sri City Infrastructure Development (viii)
  • Orders on petition filed by M/s Raghu Rama Renewable Energy Ltd(ix)
  • Orders on petition filed by M/s MMS Steel & Power Private Limited
  • Orders on petition filed by M/s TCP Limited (ii)
.
Performance Highlights of NTPC during 2008-09
.
R V Shahi's Weekly Column for Infraline - Uncertainties on Reorganisation of State Electricity Boards Must End (April 20, 2009)
.
Profile of Lanco Kondapalli CCPP Expn. Stage-II

The project is the expansion stage-II of the Lanco's power project at Kondapalli, promoted by Lanco Kondapalli Power Pvt Ltd. The project has installed capacity of 366 MW, which will be developed in configuration of one unit of GT-1 233 MW and ST 133 MW. The project would entail investment of Rs 1188 crs.

.
RERC - Tariff Order for FY 2008-09 (March 29 to 31 2008)

The Following Orders have been released by RERC :

  • Determination of Wheeling Charges & Cross Subsidy Surcharge for FY 2009-10.
  • Order on State Advisory Committee.
  • In the matter of petition filed by M/s RVUN for determination of tariff for MYT control period FY-10 to FY-14 and ARR for FY 10.
  • In the matter of petition filed by M/s RVUN for determination of tariff for MYT control period FY-10 to FY-14 and ARR for FY 10.
  • In the matter of determination of ARR & Tariff for the FY 2008-09 of Rajasthan Rajya Vidyut Prasaran Nigam Ltd.
.
Updated status of Konaseema CCPP as on March 2009
Konaseema Gas Power Ltd. is the promoter of the Konaseema CCPP. The project is located in East Godavari district of Andhra Pradesh. The project consists of name plate capacity of 445 MW. The construction of project is completed in all respects. The project has critical issue related to availability of regular gas by GAIL.

.
Updated status of GVK's Gautami CCPP as on March 2009

GVK has developed the 464 MW Gautami combined cycle power plant located at Peddapuram in East Godavari District of Andhra Pradesh at a cost of Rs rs 1935.13 crs. Construction of project completed in all respects. Project has critical issue of availability of regular gas by GAIL.

.
Infraline PLUS - CERC restructures Unscheduled Interchange Regime: The Right Step Forward (April 20, 2009)
.
A complete Status note on Issues Concerning RGPPL (As on April 15th, 2009)

Following a row of meetings held by Ministry of Power (MoP) and all stakeholders of RGPPL, namely GoM, MSEDCL, NTPC, GAIL and lenders to resolve the pending critical issues for ensuring the overall project viability, the key components of viability framework discussed and agreed upon by all the stakeholders for revival of the project, which are detailed in the document.

.
PSERC - Petition regarding implementation of State Grid Code, requirement of CTs and PTs for metering and requesting time for the same (March 30, 2009)

Tariff Order released by PSERC :

  • Punjab State Electricity Board (Board) has filed this petition seeking additional time for fulfilling the requirements of the State Grid Code (SGC) in respect of Current Transformers (CTs) and Potential Transformers (PTs). The Commission, in its order of 8.1.2008 directed that the Board may obtain the recommendations of the State Grid Code Review Committee (SGRC) and submit the same for its consideration. More>>
.
PSERC - Tariff Order for FY 2008-09 (March 24 to 30, 2009)

The Following Orders have been release by PSERC:

  • Petition for Continuation of Tariff as revised by the Commission vide its Order 3.07.2008 after 31.3.2009 till the time ARR/Tariff for 2009-10 is determined by the Commission. 30.03.2009

  • Petition No.14 of 2008 under Section 94 of the Electricity Act, 2003 for review of Punjab State Electricity Regulatory Commission Tariff Order dated July 3, 2008 of 2008-09. 24.03.2009

.
CERC - General Order for FY 2009-10 (April 09 to 16, 2009)

The Following Orders have been released by CERC -

  • Application for grant of transmission licence to Teestavalley Power Transmission Ltd. (TPTL). Teestavalley Power Transmission Ltd, New Delhi (16.04.2009)

  • Maintenance of Grid Discipline - Compliance of provisions of the Indian Electricity Grid Code. Transmission Corporation of Andhra Pradesh Ltd.,  Hyderabad (ii) (13.04.2009)

  • Maintenance of Grid Discipline - Compliance of provisions of the Indian Electricity Grid Code. Tamil Nadu Electricity Board, Chennai (13.04.2009)

  • 1. Unlawful and arbitrary denial by Tamil Nadu Electricity Board for granting concurrence for Open Access sought by Tata Power Trading Company Limited.1. Tata Power Trading Company Limited, Mumbai 2. DCW Limited, Mumbai
    2. Wilful violation of Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008 DCW Limited, Mumbai (09.04.2009)

.

More recent updates ....

 


  
>> | Oil & Gas ( 17 News Items)

Natural Gas

Reliance Industries inks gas supply agreements from KG-D6 fields with power firms including Essar Power and an Anil Ambani Group firm
Infraline.com
  • Reliance Industries has inked deals to supply gas from its eastern offshore KG-D6 fields to most power sector consumers, including Essar Power and an Anil Ambani Group firm. However, it is yet to sign the Gas Supply and Purchase Agreement (GPSA) with state-run NTPC Ltd and Ratnagiri Gas and Power, the owner of the Dabhol power plant. NTPC is to get 2.67 million cubic metres per day of gas from KG-D6 while Dabhol has been al located 2.7 mmcmd.

  • Ratnagiri Gas and Power cannot immediately take KG-D6 gas and so it has not signed the GSPA, which has provisions of take-or-pay,'' a Government official said. "In the case of NTPC, RIL has sent a draft GSPA and the agreement is likely to be signed soon. ''

  • The power sector had been allocated 18 mmcmd gas out of the initial 40 mmcmd volumes from KG-D6. Gas of 6.22 mmcmd would go to eight power plants in Andhra Pradesh, the landfall point of the gas from the Bay of Bengal fields. Essar's 300 MW power plant in Gujarat will get 1.08 mmcmd while ADAG's 220-MW Samalkot plant in Andhra Pradesh will get 0.19 mmcmd. Gas will be sold at government-approved rates of USD 4.20 per million British thermal unit plus taxes and transportation, the official said. Company officials could not be reached for comments.

Source

[Top]
Essar Power requests for supply of D6 gas at Hazira instead of Vapi
[Source : Infraline News Team]
  • Essar Power has requested MoP&NG to direct RIL to supply 1.08 MMSCMD of D6 gas at Hazira instead of Vapi.  In the case of GTA, RIL has stipulated that the gas will be made available at Vapi from where Essar will have to make arrangement with GSPL for transmission of gas from Vapi to its Power Plant at Hazira. For this, Hazira will have to enter into a Transmission agreement with GSPL which insists on entering into a long term Ship or Pay Transmission agreement.

  • As per the GSPA with Reliance, there is no binding obligation on Reliance for supply of the gas as there are no such provisions in the proposed agreement. As per the agreement, Reliance can stop gas supplies with a maximum liability of 30 days. In view of this, Essar now finds it extremely difficult to enter into Ship or Pay long term transmission agreement with GSPL.

  • Essar has now requested MoP&NG to direct RIL to deliver the gas to Essar at Hazira has RGTIL has extended its East West pipeline to Hazira and has setup a gas receiving station from where Essar can carry the gas through its pipeline to its Power Plant at Hazira.

Source : Infraline News Team

[Top]
Reliance Industries Limited (RIL) has signed Gas Sales and Purchase
[Source : Infraline News Team]
  • Agreement (GSPA) with the customers in power sector for supply of natural gas to be produced from the KG-D6 block. The GSPAs were signed with 9 customers in the power sector for supply of approximately 11.0 million standard cubic meters (mmscmd) natural gas at 11 different power generation facilities.

  • The key highlights are:

    • The duration of contract under the GSPA is 5 years.

    • The gas price in GSPA is as per the formula approved by the Government.

    • Gas to the customers would be transported through the East-West Pipeline of Reliance Gas Transportation Infrastructure Limited (RGTIL) and through pipelines of GAIL and GSPL.

    • The power companies also signed Gas Transportation Agreement (GTA) with RGTIL. The list of power companies with whom GSPA were signed is Annexed. RIL expects to sign GSPA with other power companies shortly, which is expected to increase the contracted quantity of gas for the power sector to 18 mmscmd.

Source : Infraline News Team

[Top]
Ministry issues final list for Power Customer eligible to receive D6 gas till September 2009
[Source : Infraline News Team]

Ministry has issued the final list for Power Customer eligible to receive D6 gas till September 2009 in accordance with the approved guidelines for sale of natural gas. While issuing this list, MoP&NG has observed that due to capacity constraint on Gas Rehabilitation Expansion Programme (GREP), the gas earmarked for NTPC at Faridabad and Dadri in the list detailed below should be supplied to other plants of NTPC, till GREP expansion is completed. Directions regarding the same would be issued separately.

Further, MoP&NG has observed that the supply of D6 gas to inter-alia NTPC's existing gas based plants in the list should be made at the price earlier approved by EGOM.

Name of Power Station Gas Allocation from D6 field
Kondapalli 0.27
Jeguurpadu CCGT (GVK) 0.15
Jeguurupadu CCGT (GVK) Ext. 0.82
Samlkot CCPP / Paddapuram 0.19
Vemagiri CCPP 1.38
Gautami CCPP 1.73
Konaseema CCPP 1.66
Faridabad CCGT 0.13
Anta CCGT 0.13
Dadri CCGT 0.45
Kawas CCGT 1.76
Gandhar CCGT 0.30
Dhuvaran CCPP (GSEL) Extn. 0.36
Uran CCGT 0.32
Vatwa CCGT (Torrent Power) 0.32
GPEC - Paguthan CCGT 0.97
GIPCL - Stage II CCGT 0.01
Essar IIMP CCGT 1.08
Sugen Torrent 2.74
Total 15.28

Source : Infraline News Team

[Top]

Petroleum Refining & Marketing

Indian Oil Corp plans to shut half of its 240,000 bpd refinery for 45-50 days in March and April next year to raise its capacity to 300,000 bpd
Infraline.com
  • Indian Oil Corp. (IOC) plans to shut half of its 240,000 bpd refinery for 45-50 days in March and April next year to raise its capacity to 300,000 bpd, its director for refineries, B.N. Bankapur, said on Tuesday (April 28). "It will be a major shutdown. We were planning to do it in December but we now plan to do it in March-April because of high seasonal demand for refined products in December," he said. He said the refinery would shut one 120,000 bpd crude distillation unit as well as a hydrocracker and a delayed coker unit.

Source

[Top]
India's crude oil imports and local sales of refined products expanded at slowest pace in three years in 2008/09 - Declining growth pared demand
  • India's crude oil imports and local sales of refined products expanded at the slowest pace in three years in 2008/09, as declining growth in Asia's third-largest economy pared demand, government data showed. Asia's No. 3 oil consumer's crude imports in 2008/09 rose 5.3 percent to 2.56 million barrels per day (bpd), helped by the commissioning of Reliance Industries' 580,000 bpd refinery in Western state of Gujarat in December. The new unit, situated next to Reliance's 660,000 bpd refinery, turned Jamnagar into the world's biggest oil complex.

  • Indian energy demand is expected to rise in April and May as the use of vehicles for a general election will lift diesel sales, while the low-priced Nano car being introduced this year is likely to raise gasoline demand. In March crude oil imports grew 11.7 percent to 2.77 million bpd. Oil sales rose 3.5 percent in 2008/09, while global crude oil prices shedding close to $100 dollar a barrel from the July peak on a global economic slowdown.

  • But in March India's oil product sales rose 3.9 percent to 12.19 million tonnes because of a slight revival in some sectors of the economy such as cement, steel and automobiles, and higher use of auto fuels for the election campaign. The Indian economy is expected to have grown at its slowest pace in six years in the 2008/09 fiscal year that ended in March, with the expansion projected to slow down further in the current year.

  • Diesel sales in March grew 8.8 percent to 4.8 million tonnes and petrol consumption rose 13.2 percent. The International Energy Agency in a report has said the outlook for petrol demand in India was promising as consumer appetite for new cars expected to remain strong. "The launch in late March of Tata Motors' Nano, a low-cost, no-frills car, should contribute to making transportation relatively affordable for large swathes of prospective Indian drivers," it said.

  • India exported 10.7 percent less oil products in 2008/09 than year ago on weak global oil demand and refining margins. In March exports declined 7.7 percent to 3.14 million tonnes than a year earlier. India imported 18.29 million tonnes of oil products in 2008/09, a decline of 19.2 percent on year, as private refiner Essar Oil supplied products to state-firms. Imports in March fell 36.6 percent from the same month a year earlier to 1.18 million tonnes. Diesel imports declined 35.1 percent in March to 187,500 tonnes, taking the total for the year to 2.73 million tonnes, down 7.3 percent from year before.

Source

[Top]
Global oil refining margins slow to recover - No immediate signs of significant recovery to peaks achieved in past years, says survey
  • Weak demand and surplus refining capacity is likely to keep refining margins low this year with no immediate signs of significant recovery to peaks achieved in past years, a Reuters survey of analysts found. A fall in wholesale oil product prices has exceeded that in crude oil, which have slid by about $100 a barrel since summer last year, as global oil product demand has been falling sharply amid economic recession this year, squeezing oil refiners' profit.

  • The International Energy Agency estimates the fall will be at the fastest rate since the 1980s. The survey of six banks showed refining margins, indicators for oil refiners' profit levels, in Europe, including the Mediterranean, will average in a range from $1.07 to $5.14 a barrel, putting a mean forecast at $3.84 for 2009.

  • Margins were expected to average in a range from $7.17 to $8.45 a barrel this year in the U.S. Gulf coast, the oil industry hub in the world's top consumer the United States, the survey showed. Asian margins were likely to average $4.60-$5.76 a barrel. "Soggy demand and emerging supply overhangs in certain markets/products places risk on the downside," Citigroup wrote in a research note.

  • The U.S. Gulf margins averaged in a range of $9.90-$13.01 a barrel last year depending on the methodology each banks used to calculate margins. In Europe margins averaged a wider range of $2.18 and $10.84 last year. Some old European plants typically post lower profit than modern plants due to lack of refining units to convert loss making heavy fuel oils to more profitable light products, such as gasoline and diesel.

  • Margins were expected to recover slightly next year but will be nowhere near close to their peaks in 2007 in the United States and 2008 . Some analysts expected a modest rise in crude oil prices, but refined oil products to lag behind due mainly to increasing supplies from new plants mainly in Asia, such as Reliance Industry's Jamnagar in India, which have already started capping a rise in product prices.

  • The Jamnagar refinery will become the world's largest when it fully comes on stream later this year. Most analysts expected margins to fall the most sharply in Europe as a direct result of the additions of new capacity as demand in the region wqs seen as falling more quickly than most other areas of the world.

  • Morgan Stanley expected margins in Northwest Europe to average $4.00 a barrel this year, compared with less than half of the $8.47 average last year, and recover to $5.50 in 2012. "The world is long refining capacity right now -- and the world will now have to find room for the output of several new refiners, including the huge 580,000 barrels per day Jamnagar plant in India," Morgan Stanley said in its research note. "The arrival of new refining capacity in the face of weak demand leaves us bearish on margins overall, and therefore crude demand."

Source

[Top]
IndianOil, Hindustan Petroleum and Bharat Petroleum walk the tightrope for 2008-09 - Ministry hopeful of positive show by companies
  • IndianOil, Hindustan Petroleum Corporation and Bharat Petroleum Corporation are literally walking the tightrope as they set about finalising their accounts for 2008-09. Indications are that while IOC and BPCL could sail through, the going may be tough for HPCL which posted a loss in the third quarter of last fiscal.

  • However, the Petroleum Ministry is optimistic that the trio would end the fiscal on a positive note. The Petroleum Secretary, Mr R.S. Pandey, said, “We are hopeful that the oil companies would not go into losses following the compensation package worked out by the Government.” One of the biggest concerns for the three refiners is their combined mark-to-market losses on the oil bonds estimated at nearly Rs 5,000 crore. “This is happening because the second and third tranche of oil bonds were issued at a low coupon rate of 6.5 per cent,” an oil industry executive said.The other relates to forex losses (on crude and product imports) incurred due to the “extraordinary volatility of the rupee” which work out to roughly Rs 8,000 crore. In addition, there are inventory losses to be accounted for. The trio had bought crude when prices had crossed $100 per barrel and were stuck with expensive stocks when it had crashed by over 50 per cent. According to top sources, the combined losses are believed to be around Rs 6,000 crore.This is not all. The three oil companies had to borrow heavily during the first nine months of the previous fiscal and the interest on these loans is in the region of Rs 8,500 crore. “The bonds were only issued in December 2008 by which time our borrowings had piled up,” they add. The Centre is not likely to make good any of these losses. At best, it will only compensate the oil majors for the balance portion of the under-recoveries (losses arising from selling petrol, diesel, kerosene and cooking gas at subsidised prices), which works out to a little over Rs 10,000 crore.For 2008-09, the total under-recoveries aggregate Rs 1,03,182 crore of which Rs 92,967 crore has been reimbursed to IOC, BPCL and HPCL in the form of oil bonds (Rs 60,967 crore as on February 11) and additional support, in the form of discounts on crude and products, from the Oil and Natural Gas Corporation (ONGC), GAIL (India) and Oil India for the first three quarters (Rs 32,000 crore). “It is only the balance Rs 10,215 crore which the Centre will reimburse us. All other losses will have to be written off in our books,” an oil company official said.What has raised the hackles of the three refining companies is the fact that they have had to take the rap for interest costs as well as the mark-to-market losses on the oil bonds. “All this boils down to the timing of the issue of these oil bonds. In the first place, they were given to us a good 11 months into calendar 2008 when we were bleeding and had already borrowed heavily. To make things worse, we have had to incur losses totalling Rs 3,000 crore when the bonds were sold,” the official added.

Source

[Top]

Exploration & Production

Petronet LNG plans to go upstream through acquisition of stakes in gas fields in Papua New Guinea and Australia in partnership with ONGC
Infraline.com
  • Petronet LNG, which is the country’s biggest natural gas importer, plans to go upstream through acquisition of stakes in gas fields in Papua New Guinea and Australia, in partnership with ONGC. It also plans to set up gas liquefaction plants in the two regions, involving a total investment of up to $20 billion. The company is looking at these so-called farm-in arrangements for gas fields with total reserves of 7-12 trillion cubic feet (tcf) gas. These reserves would be able to support a 5-7 million tonne liquefaction plant for a 25-year period. Setting up of a plant of this capacity typically involves an investment of $8-10 billion and could take at least 5-6 years.“The company is serious about going upstream. The due diligence at both these locations is over. The talks on financial valuation will begin shortly. The purpose behind this initiative is to secure an independent source of energy supply for India and curb the volatility in delivered gas prices,” P Dasgupta, managing director and CEO of Petronet LNG said. The process is likely to be over by this calendar year.“We plan to set up a liquefaction plant in Papua New Guinea, where the gas fields are onshore. A similar plant might be set up in Australia at a later stage, where the gas fields are offshore. The purchase of stake in gas fields and setting up of liquefaction plants would require a total investment of as much as $32-40 billion, which will be funded through a mix of debt (70 per cent) and equity (30 per cent). “ONGC will bring in its expertise in upstream exploration as well as the investment. But we will need to get more equity partners since the investment size is huge,” said Dasgupta.

Source

[Top]
RIL Signs Additional Gas Sales Agreements, MA Oil production resumes
  • In addition to the previously announced fertilizer sector agreements (530 MMcfd), RIL and Niko Resources have now signed 11 gas sales agreements (390 MMcf/d) with the power sector.  The D6 block now has 920 MMcf/d under five year contracts.  The price is USD$4.20 per mmbtu net.
  •   MA oil production has resumed following a scheduled shut down to allow tie-in modifications for its next set of horizontal wells.

Source

[Top]
ONGC Performance Highlight for March, 2009 - I: Highlights
Infraline.com
  • Exploratory well B-12-12 (B-12-P) drilled in C-Series PML of Mumbai Offshore Basin drilled to explore the hydrocarbon potential of Mahuva and Daman formations, on conventional testing flowed gas @ 1,64,673 m3/d with condensate & emulsion @ 335 bbl/d through 3/8" choke from Object-I (Int 2468-2463.5) within Daman Formation. The testing result has provided is a lead in C-Series PML area and will help in extending the reserve estimation limit and open up scope to explore such locales in the area.

  • Exploratory well YS-5-1A, substitute location for YS-5-1(YSAF), was drilled in PEL block IE to explore the hydrocarbon potential of Miocene sub-unconformity, Lower Cretaceous rift fill and fractured basement. Based on the log interpretation, geological data and MDT results two objects were identified for testing. On conventional testing, Object-ll (Int 3968-3947 m) flowed gas @ 54203 m3/d alongwith traces of oil (6mm bean). Object-I did not become active and yielded formation water (salinity: 11.4 gpl) on reverse out. The testing result has established a new prospect discovery and has given impetus to the exploration in deeper Cretaceous sequences.

  • Exploratory well Charali-36 within Charali PML in A&AA Basin was drilled to explore Tipam (TS-4 & TS-5) and BCS Formations. On conventional testing Object-ll (Int 3107.5-3105 m) in BCS Formation flowed gas @ 67,197 m3/d with condensate @14.5 m3/d through 6 mm bean. This is a new pool discovery which has established hydrocarbon potential in BCS sand in the northern part of Charali Structure.

  • Exploratory well, Matar-11 in Dabka-Sarbhan PEL of Cambay Basin was drilled to explore potential of Hazad Formation. On conventional testing flowed oil in surges from Object-ll a (1763-1759 m) & Object-ll b (1757-1755 m. The total influx of oil was 9.3 m3. Object-Ill (Int 1753-1750 m) flowed oil @ 72 m3/d & gas @ 6,900 m3/d through 6 mm bean. This was a new pool discovery in Matar area has opened up the Eastern Margin for further exploration of fault-closure plays.

  • Exploratory well, Charada-3 located within Charada PEL (Mehsana) in Cambay Basin was drilled to a depth of 759 m. MDT carried out in the intervals 416.9-416.8 m and 452.5-452.4m yielded indications of hydrocarbons. Of the four objects identified for testing, two objects were tested. Object-I (Int 758-616 m) on barefoot testing produced thick & viscous oil (API Gravity: 13.2). Object-ll (Intervals 599.5-592.5, 577-563, 549-547, 538-534, 529-526 & 524-521 m) on conventional testing also produced approximately 505 litres of thick & viscous oil (API Gravity: 13.2) on compressor application after steam squeeze job. After soaking with chemicals, it produced 3.5 m3 heavy oil.

  • Well Gandhar-607, in Ankleshwar, drilled to explore Hazad Member on conventional testing flowed oil @ 22 m3/d & gas @ 1722 m3/d through 4mm bean from Object-I (Int 3149.5-3144.5 m) in Hazad Member (GS-1). The testing result has established the extension of GS-1 pay sand towards south.

  • Well Bokaro-1 located in CBM block BK-CBM-2001/1 in Jharkhand was drilled to a depth of 1199 m with an objective to establish the CBM potential/reducibility of major coal seams through capturing of various geological reservoirs and production parameters.

  • Seven objects were identified for testing. Object-IV (Int 716-697 m) after dewatering flowed maximum gas @ 15,225 m3/d with water 14 m3/d. The maximum gas rate was 7281 m3/d from commingled production of Object I to IV.

  • Further details are available in Infraline Oil and Gas sector database

Source

[Top]
ONGC Performance Highlight for March, 2009 - II: Seismic at 146percent of target
Infraline.com

Seismic Survey: Seismic survey achievement during the month was 9561 LK (132%) against target of 7270 LK for 2D survey and 5309 Sq. km (146%) against a target of 3643 Sq. km for 3D survey. Cumulative achievement for the year 2008-09 has been 77,125 LK (140%) against a target of 54,935 LK for 2D and 26,782 Sq. km. (117%) against a target of 22,822 Sq. km. for 3D.

Seismic Surveys

(Provisional)

Basin Type Plan (BE) March 2009 Cumulative for 2008-09
(Unit) 2008-09 Target Actual % Target  Actual  %
Onland
Cambay 2D (GLK) 0 0 0 - 0 30 -
3D (SKM) 1650 260 200 77 1650 1459 88
Rajasthan 3D (SKM) 330 51 39 76 330 258 78
KG 3D (SKM) 1355 135 202 150 1355 1268 94
Cauvery 3D (SKM) 1114 0 0 - 1114 1359 122
Assam Shelf 2D (GLK) 260 70 0 0 260 35 14
3D (SKM) 795 20 5 27 795 73 9
AAFBA 2D (GLK) 0   93 -   116 -
3D (SKM) 569 17 140 826 569 612 108
MBA 2D (GLK) 525 0 0 - 525 924 176
3D (SKM) 350 100 204 204 350 494 141
Ganga Valley 2D (GLK) 685 0 75 - 685 281 41
Vindhyan & Gondwana 2D (GLK) 1035 100 194 194 1035 887 86
3D (SKM) 66 15 0 0 66 0 0
Sub-total 2D (GLK) 2505 170 362 213 2505 2274 91
3D (SKM) 6229 598 791 132 6229 5524 89
Offshore
Gulf of Cambay 2D (LK) * 0 0 160 - 0 571 -
Western Offshore 3D (SKM) 1250 160 264 165 1250 887 71
2D (LK) * 3500 0 0 - 3500 10475 299
3D (SKM) * 2643 100 1862 1862 2643 5579 211
Krishna Godavari 2D (LK) * 21632 3600 4784 133 21632 32806 152
3D (SKM) * 5260 1110 0 0 5260 1260 24
Cauvery 2D (LK) * 27298 3500 4255 122 27298 30998 114
3D(SKM)* 3660 1400 619 44 3660 1306 36
Mahanadi 3D(SKM)* 2650 275 1774 645 2650 7100 268
Andaman 3D (SKM) * 1130 0 0 - 1130 5126 454
Sub-total 2D (LK) 52430 7100 9199 130 52430 74850 143
3D (SKM) 16593 3045 4518 148 16593 21258 128
ONGC 2D (LK) 54935 7270 9561 132 54935 77125 140
3D (SKM) 22822 3643 5309 146 22822 26782 117

* Contractual, ^AAFB includes Tripura & Cachar

Major reasons for shortfall:

Cambay: 3D: 3D outsourcing has been dropped
Rajasthan: 3D: Logistic problems in sand dunes affected movement of Vibrators.
KG. 3D: Movement of parties delayed due to non-availability of explosive licence in time.
Assam Shelf: 2D & 3D surveys affected due to delay in mobilization of crew by contractor in Nagaland due to administrative problem & extreme logistics.
Ganga Valley and 2D survey during the year was affected due to frequent instrument problem & poor
Vindhyan & Gondwana: performance of shot hole drilling contractor.
W. Offshore: 3D: Dept. survey affected due to streamer problems
KG Offshore: 30: Acquisition in NELP-VI blocks shifted to BE-2010-11
Cauvery Offshore: 3D: Acquisition in NELP-VI blocks shifted to BE-2010-11.

Source

[Top]
ONGC Performance Highlight for March, 2009 - III: 46 wells drilled against 64 wells target
  • Drilling: A total of 41 wells (64%), 26 in Onshore & 15 in Offshore, were drilled during the month against the target of 64 wells (40 in Onshore & 24 in Offshore). Cumulative achievement for the year 2008-09 has been 326 wells (83%), 243 in Onshore & 83 in Offshore, against the target of 394 wells (269 in Onshore & 125 in Offshore). In Onshore, annual target of exploratory wells has been achieved in Western Onshore and that of development wells in Western Onshore, Rajahmundry & Cauvery. Shortfall has been mainly in exploratory wells in A&AA, KG, Cauvery and development wells in Assam mainly on account of non-availability of planned charter hired rigs, extended production testing; well complications and capital repairs.

  • In Offshore, annual target of exploratory wells has been achieved in KG shallow water and that of development wells in Mumbai High. Shortfall in exploratory wells has been mainly in Gulf of Cambay where locations have been taken-up for drilling from Onshore & also due to delay in environmental clearance; and in Mumbai shallow water mainly due to non-availability of charter hired rigs. Shortfall in development wells in Neelam-Heera & Bassein Assets has been due to delay in installation of new platforms and also on account of batch drilling of wells. Shortfall in deepwater drilling has been on account of non-availability of rigs.

Drilling: Exploratory Wells

Basin Plan (BE) March 2009 Cumulative for 2008-09
2008-09 Target Actual % Target Actual %
Ahmedabad 9 4 2 50 9 10 111
Mehsana 9 1 0 0 9 9 100
Ankleshwar 10 5 3 60 10 13 130
Cambay 4 0 1 - 4 4 100
Rajasthan 2 1 0 0 2 1 50
Western Onshore 34 77 6 55 34 37 709
Upper Assam 13 0 1 - 13 7 54
Jorhat 11 1 1 100 11 4 36
Silchar 3 1 0 0 3 1 33
Tripura 7 3 0 0 7 4 57
Assam & Assam Arakan 34 5 2 40 34 16 47
Bengal Onshore 1 0 0 - 1 0 0
Bengal (SW) 0 0 0 - 0 2 -
Mahanadi (SW) 0 0 0 - 0 0 -
Mahanadi (DW) 4 1 0 0 4 0 0
Andaman (DW) 4 1 0 0 4 0 0
Mahanadi Bengal Andaman 9 2 0 0 9 2 22
KG (Onshore) 19 5 2 40 19 9 47
KG (SW) 9 0 1 - 9 9 100
KG (DW) 7 2 0 0 7 0 0
Krishna Godavari 35 7 3 43 35 78 57
Cauvery (Onshore) 16 3 2 67 16 11 69
Cauvery (SW) 0 0 0 - 0 1 -
Cauvery (DW) 3 1 0 0 3 2 67
Cauvery 19 4 2 50 79 74 74
Himalayan Foreland/GV 2 1 0 0 2 1 50
Vindhyan & Gondwana 1 0 0 - 1 0 0
GVK (Frontier) 3 7 0 0 3 7 33
Mumbai (SW) 19 5 5 100 19 17 89
Kutch-Saurashtra (SW) 1 0 0 - 1 2 200
Kerala Konkan (SW) 2 0 1 - 2 1 50
Western Offshore (SW) 22 5 6 720 22 20 97
Gulf of Cambay (SW) 5 1 0 0 5 0 0
Deepwater West Coast 1 0 0 - 1 0 0
Deepwater East Coast 78 5 0 0 73 2 77
Deepwater (E & W Coast) 79 5 0 0 79 2 77
Onshore 107 25 12 48 707 74 69
Offshore 55 77 7 64 55 34 62
ONGC 162 36 19 53 162 108 67

SW: Shallow Water, DW: Deep Water

Major reasons for shortfall during 2008-09:

  • Rajasthan: Production testing of 9 objects against 4 planned in well BLT-1; waiting on civil works / material.
  • Upper Assam: Non-availability of one charter hired rig planned for exploratory drilling, complication in 6 wells & extended production testing at 1 well & bandh / barricade / waiting on ready site.
  • Jorhat: Extended production testing at 2 wells; unplanned capital repairs at 2 rigs & diversion of rig to unplanned dev. drilling (completed 1 well); bandh / barricade / waiting on ready site.
  • Silchar: Complication in 1 well. - Tripura: Non-availability of 1 CH rig & diversion of rig to Dev. drilling.
  • Bengal (On): Non-availability of ready site. - Frontier: Delayed deployment of 1 rig & Non-availability of 1 CH rig.
  • KG (On): Non-availability of 2 planned Charter hired rigs, diversion of rig to development drilling, complication in 1 well, unplanned deployment of rig E-2000-1 at well NSN-AA with out completing well SUAE; prolonged testing at 2 wells; extension of target depth of 3 wells.
  • Cauvery (On): Prolonged testing at 3 wells, unplanned capital repair of Draw works of rig E-1400-9, delay in civil works at 3 locations & non-availability of planned charter hired rig.
  • Mumbai (SW): Complication in well B_209#A (abandoned), unplanned diversion of rig to Bengal SW{2 wells completed in Bengal SW), waiting on weather, delayed availability of 3 rigs (CE Thronton, S/Shakti & Ratna), non-availability of charter hired rigs, non-availability of 2 rigs (S/Gaurav due to prolonged drydocking and Energy Driller deployed for recovering BOP & salvaging of well G_1#DB in KG Offhore) and Rig S/Kiran could not be positioned at location due to unfavorable weather & problem in jetting system .
  • Deep Water: Delayed hiring of planned deepwater drilling rigs and non-hiring of 3 planned rigs due to non-availability.
  • Gulf of Cambay: Delayed receipt of Env. clearance for taking up location (Gulf G-1). 2 locations taken up by Onshore rigs and metreage & wells being accounted in Ankleshwar. Delay in soil coring reports

Drilling: Development Wells

Asset Plan (BE) March 2009 Cumulative for 2008-09
2008-09 Target Actual % Target Actual %
Ahmedabad 55 2 4 200 55 60 109
Mehsana 32 1 2 200 32 37 116
Ankleshwar 21 2 1 50 21 27 129
Cambay 6 1 1 100 6 7 117
W. Onshore 114 6 8 133 114 131 115
Assam 30 7 4 57 30 13 43
Jorhat 0 0 0 - 0 1 -
Tripura 1 0 0 - 1 2 200
Rajahmundry 10 2 2 100 10 15 150
Cauvery 7 0 0 - 7 7 100
Onshore 162 15 74 93 162 769 104
Mumbai High 22 4 3 75 22 24 109
Neelam-Heera 18 3 1 33 18 5 28
Bassein & Satellite * 30 6 4 67 30 20 67
Mumbai Offshore 70 13 .8 62 70 49 70
ONGC 232 28 22 79 232 218 94

* Includes Marginal fields

Reasons for Shortfall during 2008-09:

  • Assam:
    • Non-availability of 3 charter hired rigs & 1 rig (BI-2000) from W. Bengal planned for development drilling;
    • complication at 2 wells; delay in civil works at 1 location; bandh/ barricade / waiting on ready site.
  • Mumbai Offshore:
    • Delay in installation of new platforms - HSC, HJ, HI & C-39.
    • Due to the introduction of Rotary Steerable System (RSS) & Synthetic Oil Based Mud system (SOBM), all the wells on a platform are being 'batch drilled' up to 12 1/4" & 8 1/2" phase instead of completing single well, and would subsequently be taken up for completion.
    • In view of reduced down-hole complications observed in wells drilled with SOBM, more number of wells than envisaged are being taken up with SOBM. At any given time 2 to 3 rigs can be taken up for SOBM resulting in waiting of some wells for SOBM. 9 such wells are waiting for SOBM.
    • Performance also affected due to waiting on weather & logistics support.

Source

[Top]
ONGC Production and Sale highlights for March, 2009 - IV: Oil lags, gas slightly better
  • Crude oil production during the month was 2.120 MMt (83.3%) against the target of 2.547 MMt. Cumulative achievement for the year 2008-09 has been 25.366 MMt (92.8%) against a target of 27.323 MMt. Production during the year was mainly affected due to less input in number of development/ sidetrack wells & insufficient logistics support in Mumbai Offshore; shut down at NQG (Dec'08); delay in installation of new platforms in Heera; high water cut in wells of VW platform, delay in installation of processing platform for VSEA wells & shutdown taken for hook-up of BCPA-2 platform in Bassein; delay in G-1 & GS-15 project in KG Offshore. In Onshore, production was affected on account of increasing trend of water cut in Ankleshwar; decrease in reservoir pressure & increase in water cut in Ahmedabad; less gain from EOR fields & power shut down in Mehsana and due to environmental reasons in Assam.

  • LPG production during the month was 91,314 tonnes (97%) against the target of 94,182 tonnes. Cumulative achievement for the year 2008-09 has been 10,26,319 tonnes (95.6%) against a target of 10,74,000 tonnes. LPG production at Uran during the month was affected due to less gas receipt from offshore and restricted feed to LPG-I & II plants on account of problem in exchangers/coolers.

Crude Oil Production (MMt)

(Provisional)

Asset/ Basin

Plan (MOU) 2008-09

March 2009

Cumulative for 2008-09

Target

Actual

%

Target

Actual

%

Mumbai High

12.426

1.105

0.945

85.5

12.426

11.621

93.5

Neelam-Heera

3.560

0.318

0.271

85.2

3.560

3.356

94.3

Bassein & Sat.

1.052

0.226

0.069

30.6

1.052

0.819

77.8

Condensate

1.915

0.171

0.197

115.1

1.915

2.006

104.7

Mumbai Offshore

18.953

1.821

1.483

81.4

18.953

17.801

93.9

Ahmedabad

1.820

0.156

0.134

85.8

1.820

1.642

90.2

Mehsana

2.250

0.196

0.186

94.6

2.250

2.116

94.0

Ankleshwar

2.101

0.184

0.148

80.4

2.101

1.876

89.3

Cambay

0.133

0.011

0.016

139.0

0.133

0.154

115.8

Rajahmundry *

0.394

0.031

0.025

81.6

0.394

0.289

73.3

Cauvery

0.262

0.021

0.022

105.2

0.262

0.265

101.2

Assam

1.300

0.116

0.096

82.9

1.300

1.113

85.6

A&AA^

0.110

0.010

0.011

111.7

0.110

0.110

99.7

Sub-total

8.370

0.726

0.638

87.9

8.370

7.565

90.4

ONGC

27.323

2.547

2.120

83.3

27.323

25.366

92.8

Note : Figures rounded off to third decimal place;  * KG Offshore included in Rajahmundry; ^ Includes Jorhat & Silchar

Remarks:

Mumbai High:

Less input in number of development / sidetrack wells & insufficient logistics support.

Neelam-Heera:

Delay in installation of new platforms under Heera Redevelopment Project, leading to delay in drilling of wells. HC wells closed for safety, as subsidence observed near the Platform.

Bassein & Sat.

High water cut in wells of VW platform & delay in installation of processing platform for VSEA wells. Shutdown for hook-up of BCPA-2 platform.

Ahmedabad :

Decrease in reservoir pressure & increase in water cut.

Mehsana :

Power shut downs.

Ankleshwar:

Increasing trend of water cut.

Rajahmundry:

Production commenced from 2 wells against 8 anticipated in offshore.

Assam:

Production affected due to environmental reasons.

Source

[Top]
ONGC Production and Sale highlights for March, 2009 - V: Gas production and sale perform slightly better
  • Gas production during the month was 1996.004 MMm3 (103%) against the target of 1938.100 MMm3. Cumulative achievement for the year 2008-09 has been 22489.478 MMm3 (103%) against a target of 21841.965 MMm3.

  • Gas sale during the month was 1570.304 MMm3 (107.2%) against the target of 1464.818 MMm3. Cumulative achievement for the year 2008-09 has been 17708.934 MMm3 (103.7%) against a target of 17084.770 MMm3.

 

Gas Production (MMSCM)

(Provisional)

Asset/ Basin

Plan (MOU) 2008-09

March 2009

Cumulative for 2008-09

Target

Actual

%

Target

Actual

%

Mumbai High

4814.000

426.000

418.165

98.2

4814.000

5077.698

105.5

Neelam-Heera

1052.000

91.534

113.316

123.8

1052.000

1338.202

127.2

Bassein

10333.000

944.943

979.272

103.6

10333.000

10320.519

99.9

Mumbai Offshore

16199.000

1462.477

1510.753

103.3

16199.000

16736.419

103.3

Ahmedabad

250.000

21.247

23.041

108.4

250.000

286.583

114.6

Mehsana

114.100

9.341

15.247

163.2

114.100

165.999

145.5

Ankleshwar

1475.000

127.588

127.700

100.1

1475.000

1490.376

101.0

Cambay

6.463

0.548

0.584

106.6

6.463

6.992

108.2

Rajasthan

15.000

1.320

1.380

104.6

15.000

12.526

83.5

Rajahmundry *

1675.800

135.307

125.186

92.5

1675.800

1524.166

91.0

Cauvery

1141.000

96.850

105.501

108.9

1141.000

1242.470

108.9

Assam

395.000

35.284

32.401

91.8

395.000

393.935

99.7

A&AA ^

100.602

8.950

6.846

76.5

100.602

77.347

76.9

Tripura

470.000

39.188

47.364

120.9

470.000

552.665

117.6

Sub-total

5642.965

475.623

485.251

102.0

5642.965

5753.059

102.0

ONGC

21841.965

1938.100

1996.004

103.0

21841.965

22489.478

103.0

Note : Figures rounded off to third decimal place

* KG Offshore included in Rajahmundry, ^ Includes Jorhat & Silchar

Remarks:

  • Mumbai High: Less production of associated gas
  • Rajahmundry: Less gas production from offshore

Gas Sales (MMSCM)

(Provisional)

Asset/ Basin

Plan (MOU) 2008-09

 

March 2009

 

Cumulative for 2008-09

Target

Actual

%

Target

Actual

%

Uran

3500.000

293.000

290.889

99.3

3500.000

3683.773

105.3

Hazira

8918.000

771.000

864.595

112.1

8918.000

9086.314

101.9

Sub-total (Mumbai Off)

12418.000

1064.000

1155.485

108.6

12418.000

12770.088

102.8

Ahmedabad

107.000

9.541

12.227

128.1

107.000

179.076

167.4

Mehsana

50.000

4.025

6.664

165.6

50.000

71.680

143.4

Ankleshwar

1111.890

104.189

95.366

91.5

1111.890

1119.505

100.7

Cambay

4.380

0.371

0.410

110.4

4.380

5.311

121.3

Rajasthan

15.000

1.320

1.380

104.6

15.000

12.526

83.5

Rajahmundry

1484.050

120.421

124.190

103.1

1484.050

1507.847

101.6

Cauvery

1125.000

95.500

104.782

109.7

1125.000

1230.300

109.4

Assam

243.000

21.710

18.547

85.4

243.000

214.323

88.2

A&AA^

57.450

4.634

3.997

86.3

57.450

46.704

81.3

Tripura

469.000

39.108

47.256

120.8

469.000

551.575

117.6

Sub-total

4666.770

400.818

414.819

103.5

4666.770

4938.846

105.8

ONGC

17084.770

1464.818

1570.304

107.2

17084.770

17708.934

103.7

Note : Figures rounded off to third decimal place; ^ Includes Jorhat & Silchar

Remarks: Uran: Less receipt of gas from Offshore.

Value Added Products ('000 Tons)

(Provisional)

Plant/ Asset

Product

Plan (MOU) 2008-09

March 2009

Cumulative for 2008-09

Target

Actual

%

Target

Actual

%

Uran

LPG

435.00

39.00

33.07

84.8

435.00

428.79

98.6

Hazira

LPG

578.00

49.59

54.49

109.9

578.00

560.63

97.0

Ankleshwar

LPG

61.00

5.59

3.76

67.2

61.00

36.90

60.5

Sub-total

LPG

1074.00

94.18

91.31

97.0

1074.000

1026.319

95.6

Uran

Naphtha

266.00

23.20

24.18

104.2

266.00

238.79

89.8

Hazira

SKO

145.00

12.32

12.96

105.2

145.00

146.18

100.8

Naphtha

1160.00

98.52

119.58

121.4

1160.00

1260.95

108.7

HSD

16.00

1.36

2.41

177.5

16.00

16.05

100.3

ATF

0

0

2.13

-

0

21.46

-

Sub-total

1321.00

112.19

137.08

122.2

1321.00

1444.65

109.4

Ankleshwar

Naphtha

27.00

2.37

2.29

96.8

27.00

24.69

91.5

Uran

C2-C3

510.00

48.50

39.39

81.2

510.00

496.66

97.4

Tatipaka Refinery

Naphtha

24.80

2.25

2.91

129.4

24.80

28.58

115.2

SKO

11.20

1.02

1.02

100.9

11.20

10.12

90.4

HSD

21.60

1.96

1.84

93.9

21.60

20.13

93.2

RCO

22.40

2.03

2.29

112.9

22.40

23.50

104.9

Sub-total

80.00

7.24

8.06

111.2

80.00

82.34

102.9

Cauvery

Naphtha

30.03

2.50

0

0

30.03

0

0.0

SKO

9.87

0.82

0

0

9.87

0

0.0

LSHS

2.18

0.18

0

0

2.18

0

0.0

Sub-total

42.08

3.49

0

0

42.08

0

0

Total VAP

 

3320.08

291.18

302.32

103.8

3320.08

3313.45

99.8

Source

[Top]
Asset impairment dents Aban Offshore's profitability - Company may find the going difficult as rigs have no follow-on contracts
Infraline.com
  • Aban Offshore, the country’s largest offshore oilrig service provider, reported a consolidated loss of Rs 93 crore for the quarter-ended March 2009 despite growing its revenues by over 17 per cent on a year-on-year basis. While waning demand for oil rigs and falling rig rentals resulted in four of Aban’s assets lying idle, the net loss was driven primarily by a one-off asset impairment charge of Rs 151 crore on the capital expenditure incurred on its jack-up rig Murmanskaya. Aban decided to terminate the bareboat charter of the jack-up rig (due for expiry in November) to avoid incurring the added cost, as the rig had been lying idle.Even as Aban’s consolidated quarterly revenues were up 17 per cent over last year, it declined by 8 per cent sequentially led by the idling of its rigs – due to either delay in deploying them (Aban Abraham and Aban Pearl) or completion of their old contracts. The company currently has four idle rigs with four more due to near their contract completion shortly. Considering that none of these rigs has a follow-on contract, Aban may find it difficult to deploy them any time soon as the demand for rigs (especially jack-up rigs) have fallen considerably. That said, Aban’s performance at the EBITDA (earnings before interest, tax, depreciation and amortisation) level remained healthy. EBITDA margins improved by 5 percentage points to 55.7 per cent, helped partly by the long-term contracts sealed earlier.The one-time asset impairment charge, however, wiped away the company’s operating profits. While this write-off will help the company save the cost it otherwise would have incurred in keeping the bareboat, what’s notable is that Aban decided to call off the charter months before its lapse. Saddled with a gross debt of roughly over $3.3 billion, Aban is said to be considering re-financing debt obligations as its cash flows may not be sufficient to meet the debt repayment requirements.

Source

[Top]

General

Global Opportunistic Fund II makes profit from Reliance Petroleum - Achieves an IRR of more than 70 percent through stake sale
Infraline.com
  • Global Opportunistic Fund II (GOF II), a pre-IPO and IPO fund, has made significant gains from sale of shares in Reliance Petroleum Ltd (RPL), according to a press release issued by Global Capital Management, 100 per cent subsidiary of Global Investment House, a Kuwait-based private equity group. Global Capital Management manages GOF II.

  • Mr Shailesh Dash, Managing Partner, Global Capital Management, in a release on Sunday has been quoted as saying “the fund was one of the top 10 investors, along with Chevron, Deutsche Bank, Citigroup, and Fidelity, in RPL”. However, its name did not figure in RPL’s shareholding pattern announced to the stock exchanges during the period June 2006 to March 2009. Chevron currently has 5 per cent stake unchanged and Fidelity continues to hold 1.67 per cent.Goldman Sachs, which has exited, was the only other name that figured in RPL disclosures on shareholders. “We have been liquidating our position in tranches to optimise our returns and I am happy to state that we have achieved an IRR of more than 70 per cent on this transaction and a multiple of 1.84x,” Mr Dash said, adding that the proceeds from this transaction would also be returned to the investors to ensure liquidity even in current times.Global Capital Management manages $3.2 billion of private equity assets. GOF II is now fully invested across 10 investments and has now exited four investments at IRRs between 40 and 350 per cent. The fund’s investments span 10 sectors, including healthcare, and more than 30 per cent of the fund is also invested outside the West Asia and North African region.The private equity player’s principal investment book’s annual returns, however, declined to a loss of 36 per cent against a return of 19 per cent in the previous year. Performance of its principal investment book was adversely affected by the unprecedented decline in the capital and debt markets of the Gulf Co-operation Council and the wider West Asia & North Africa region and repercussions for private investments, the firm said.

Source

[Top]

What's New in Oil & Gas Sector Database http://OilandGas.Infraline.com
 
Executive Summary of All India Inventories of Major Products (As on April 1, 2009)
.
Statewise Status of IOC's ROs LSA / RSA (March 2009)
.
Presentation on Indian Energy Sector: An Overview
.
Stats: CNG Activities in India for 2008-09 (April-September)
.
Stats: Self Sufficiency in Petroleum Products from 2006-07 to 2008-09 (April-September)
.
Stats: Statewise cumulative consumption of selected petro products during April-September 2008
.
Stats: Statewise PDS SKO Allocation vs. Consumption during April-September 2008
.
Details of crude oil import by MRPL during March 2009
.
Stats: Statewise & Category wise Retail Outlets (As of 1.10.2008)
.
Stats: Statewise/Class of Marketwise Retail Outlets (As on 1.10.2008)
.
International - Crude & Product Prices (As on April 18, 2009)
.
Stats: Statewise, Categorywise SKO/LDO Dealerships (As on 1.10.2008)
.
Subsidies and Under Recoveries on Major Petroleum Products
.
MRPL's Presentation on Quarterly Performance Review for Quarter 3 & 4, 2008-09
.
Draft GSPA signed b/w RIL and the Fertilizer Companies (April 2009)
.
IOC's Monthly Statement of Capital Expenditure (Non-Plan) during March 2009
.
HPCL's Statement of Capital Expenditure (Plan) during March 2009
.
MRPL's Performance Highlights for Quarter 3, 2008-09
.
Statewise Ethanol Supplies during November 2006 to March 2009 (Upto March 15, 2009)
.
Statewise Import & Export Fee on Ethanol (April 2009)
.
Statewise Issues on procurement of Ethanol for EBP (April 2009)
.
Stats: Average International Calorific Value of Different Fuels
.
Stats: Central Excise & Customs Tariff Table w.e.f. 31.10.2008
.
Stats: Dealers' Commission for MS, HSD and LPG (November 2002 to May 2008)
.
Stats: Estimated subsidy on Major Petroleum Products from 2005-06 to 2008-09 (Apr-Sep)
.
Bid Evaluation Criteria under NELP-VIII
.

More recent updates ....

 


  
>> | Coal ( 2 News Items)

Linkage issues

Long-term FSA between Coal India and power utilities led by navratna firm NTPC set to miss April-30 deadline on account of procedural delays
Infraline.com
  • The long-term fuel supply pact between the country's largest coal producer, Coal India, and power utilities led by navratna firm NTPC is set to miss the April-30 deadline on account of procedural delays. In a meeting between Coal India Ltd (CIL) and NTPC officials last evening, the draft of Fuel Supply Agreement (FSA) was fine-tuned and would now be sent to the boards of the two companies for approval, an official said.

  • The process of signing the FSA is likely to be completed in a month's time, he said, adding the pact between the two companies would act as a benchmark for other units to follow. When contacted, Coal India Chairman, Mr Partha S Bhattacharyya said, "All the issues (pertaining to the FSA) between both the parties have been worked out and the pact is likely to be signed around May 20.'' Earlier, CIL had set April 30 as the deadline for 72 power utilities, including NTPC, to conclude the FSA, which is a long-term supply-pact between the coal producer and consumers.

  • The pact has, however, been delayed by almost a year now due to differences over fixing of a "trigger level'', the minimum assured level of coal supply and offtakes, failing which both parties attract penalty. After a series of meetings between CIL and NTPC, the trigger level has been agreed at 90 per cent of the assured supply of 307 million tonnes (MT) to the power units, which have come up before March 31, 2009.

Source

[Top]

Mine Development

National Thermal Power Corp expects to start coal mining from its huge Pakri Barwadih block in Jharkhand in the second half of 2008-09
Infraline.com
  • Ending delays in its captive mining effort, NTPC Ltd expects to start coal mining from its huge Pakri Barwadih block in Jharkhand in the second half of 2008-09. The block was awarded to the power utility in October 2004 but several impediments related to land acquisition, forest clearance and mining operatorship resulted in a delay of at least two years in the production schedule.

  • Located in the prolific North Karanpura coalfields of Jharkhand, the PB block has estimated reserves of 1.6 billion tonnes out of which at least 700 million tonnes are mineable. Once production starts from the PB block, it would be NTPC's first step in achieving coal security. NTPC is estimated to invest around Rs 1,800 crore to bring to the PB block to production. At peak production, the block could yield 15 million tpa, although production would begin at lower levels, NTPC officials said.

  • As far as domestic reserves are concerned, NTPC has been alloted eight coal blocks with aggregate reserves of nearly 6 billion tonnes, spread over Jharkhand and Orissa (see table). Two of these-Brahmani and Chichro-Patsinal, both in Orissa-would be operated in equal partnership with Coal India Ltd. The Brahmani block is said to hold 1.9 billion tonnes of coal.

  • NTPC is also pursuing coal block acquisition in Indonesia and Mozambique, and is also part of a multi-partite special purpose vehicle “International Coal Ventures Ltd” to explore coal mining opportunities in Australia, Indonesia etc. By 2012, NTPC is expected to annually need around 225 million tonnes of coal against 130.71 million tonnes consumed in 2008-09. According to industry norms, 1 million tonnes of coal is needed to run coal-fired power capacity of 200 mw for a year.

  • By this standard, NTPC's projected coal requirement stands for 45,000 mw of coal-fired capacity. NTPC has projected to add a total power capacity (including that owned in joint venture) of 22,430 mw during the 11th Plan period (April 2007 to March 2012). Out of this, 2,740 mw was commissioned in the first two years of the Plan period, while another 3,300 mw is scheduled to commission this fiscal, 2009-10. NTPC recently crossed the 30,144 mw installed capacity mark, including 2,294 mw coming from joint venture projects (this includes gas-fired capacity).

  • By 2012, NTPC would have over 50,000 mw of power capacity—mainly coal but also including hydropower and renewable energy. Currently, domestic coal (sourced from Coal India Ltd) meets 95 per cent of NTPC's requirement of coal-fired plants, while the rest is imported. In 2011-12, NTPC expects that captive coal production would be 15 million tonnes, mainly coming from the PB block.

  • NTPC also expects to import 15 million tonnes, while Coal India and its subsidiaries would supply the bulk-195 million tonnes. It is also learnt that the mining plans for two more coal blocks have been approved by the coal ministry. These mines-Chatti Bariatu and Kerandari-are expected to together yield 13 million tonnes of coal per year. As an industry thumb rule, coal production from alloted blocks is expected to have a gestation period of 72 months, including 27 months for preparation of the geological reserve report, which is applicable in the case of unexplored or partially-explored blocks.

Source

[Top]

What's New in Coal Sector Database http://Coal.Infraline.com
 
CEA's Paper on Coal linkage for Thermal Power Projects for 12th Five Year Plan (April 2009)

TCEA has devised a methodology for recommendation of coal linkage for additional projects for 12th plan. The devised methodology has been sent to MoP for approval.

.
Proposed Guidelines for captive coal mining by allocatees by Ministry of Law and Justice (April 2009)

TLaw ministry has suggested proposed guidelines for mining of Coal by allottee companies which have been allotted captive coal blocks under Screening Committee route.

.
Performance of CMPDI during the year 2008-09

TCMPDI has achieved more than 3.31 lakh metres of drilling during 2008-09.It has prepared 20 Geological reports establishing about 2.88 BTs of coal resources to the proven category.

.
Details of Performance of WCL in 2008-09

TWCL has produced 44.70 million tonnes coal during the year 2008-09 against the target of 43.05 million tonnes i.e. 1.65 million tonnes more than target, thus achieving 103.83% over target. The company registered a growth of 2.7%, which in absolute terms is 1.19 million tonnes more than 43.51 million tonnes coal produced in 2007-08. As against a target of 32.75 million tonnes, Opencast coal production was 34.59 million tonnes which is 105.62% of the target, thus registering a growth of 3.2% over last year's 33.53 million tonnes.

.
Profile of Jharna UG expansion mine of WCL
.
Discussions on Draft Coal Import Policy by Board of NTPC ( April, 2009)

TNTPC has discussed for 3 models for coal import from overseas and finally decided on option third where in procurement of coal would be made through PSU bidders viz. MMTC/STC/CIL selected on limited tender basis for their service charges (margin).

.
Monthly and Progressive Plan Expenditure of Coal Companies (Upto February, 2009)
.
Pending cases of coal block allocation (April 2009)

TThe document gives details of three cases of allocation of coal blocks pending for final disposal in the Ministry of Coal.

.
Performance of Neyveli Lignite Corporation Limited during February, 2009
.
Review of critical coal stocks at power stations by Infrastructure Constraints Review Committee (April 2, 2009)

TThe document provides the details of the dicussion held at the 165th meeting of the Sub-Group constituted by the Infrastructure Constraints Review Committee to review the position of critical thermal power stations.

.
Profile of Penganga Opencast Coal Mine of WCL
.
Status of Paturia & Gidhmuri Coal Blocks (As on April 1, 2009)
.
Detailed Discussion of Interactive meeting of Ministry of Coal with all stakeholders ( January 22, 2009)

Tministry along with CIL discussed with all stake holders to find out the issues and probable solutions to coal supply constraints and coal block development on January 22, 2009.

.
Note on Boundary Dispute between Gare-IV/6 and IV/7 coal blocks by CMPDI (March, 2009)

TThere is an ongoing dispute for the coal blocks - Gare lV/6 and Gare lV/7 between Jindal Steel & Power Ltd and Raipur Alloys and Steel Ltd (now known as Sarda Energy Ltd) for overlap between the boundaries of the blocks. The documents provides the detailed note as prepared by CMPDI on this.

.
MoC's Comments on Revision of rate of coal royalty (March 27, 2009)
.
Infraline PLUS - Royalty on Coal (November 27, 2008)
.
Monthly Progress Report of NLC for October, 2008
.
EIL's Presentation on Overview of Technological Aspects of CTL Projects (November 2008)

.
Review of Coal Production of CIL by MoC (November 2008)

CIL made a presentation on its achievements and status of coal production in CIL at a meeting on November 12, 2008. The document lists the decisions that were taken there.

.
Profile of Bijari Opencast Coal Mine
.
List of revised captive lignite blocks for allocation by MOC (October 2008)

The document provides a detailed state-wise list of captive lignite blocks earmarked for the purpose of allocation for mining by MoC in its meeting held on October 23, 2008.

.
MoC's Note on Ganeshpur Captive Coal Block
.
List of additional projects recommended for full coal linkage under Priority-I (November, 2008)

Ministry of Power has recommended these projects (totaling to 9264 MW) who have placed order and paid advance to both the EPC contractor and BTG supplier after a detailed review of their project status.

.
Coal Availability for the Year 2008-09

It covers annual generation target,coal requirement and coal availability from all sources and the shortfall of coal requirement for the country.

.
Coal Supply Position during the period April - September 2008 vis-à-vis April - September 2007
.
Import of Coal by Power Utilities (As on October 31,2008)

The table provides the import data of coal by the power utilities as on October 31, 2008.Torrent AEC, Relaiance Energy,TNEB achieved their target set by over 100% and NTPC only achieved 17% ( 0.839MT as compared to 8.250MTs) of their import target.

.
Coal Stocks Norms for Power Stations

It gives coal stock norms for power stations as prescribed by CEA.

.
Coal Stock Position (As on November 3, 2008)

This gives comprehensive data related to normative coal stock requirement,coal stock position as on November 3, 2008,number of critical and super critical thermal power stations.

.
Major Issues related to FSA with Power Utilities

This provides in tabular form the major issues related to signing of FSA by power utilities with coal companies.

.
A presentation on Long term Coal Requirement and Availability

It covers 11th plan capacity addition program of power ministry vis a vis coal requirement for the projects queuing up.It also highlights issues related to development of coal blocks and action points related there to.

.
A presentation on Short-Term Coal Requirement & Availability for 2008-09

It covers coal availability for the year 2008-09,coal supply position, import of coal by different power companies,coal stock positions and issues related with FSA.

.
Review of Coal and Lignite Projects by MoC (September 2008)
.

More recent updates ....

 


  
>> | Telecom ( 7 News Items)

Projects

Loop Telecom's Tamil Nadu, Orissa launches next week 
  • Despite its run-in with the Ministry of Corporate Affairs (MCA), Mumbai-based GSM telecom service provider Loop Telecom will launch its services in the Tamil Nadu and Orissa circles by next week. “To comply with the norms laid down by the government, we will launch with 10 per cent coverage in Tamil Nadu and Orissa,” said a senior executive.“We will roll out in three other circles in South India within 10-15 days of our launch in the first two circles. We are not doing a large-scale commercial launch at this point in time. This is to meet regulatory requirements,” said the executive. Loop Telecom, a subsidiary of Loop Mobile (formerly BPL Mobile Comm), is one of the eight new players given a mobile service licence. Last year, the company got the licence to start GSM operations in 21 telecom circles in the country. It has been allocated spectrum in 20 circles. The licence says operators are required to cover at least 10 per cent of each district headquarters in a circle in the first year.Loop recently contracted with Chinese network equipment vendor ZTE. With next week’s launch, the company will become the first new GSM operator to launch its services, in an already crowded market. Besides the presence of incumbents like Airtel, Vodafone and Idea, the recent entry of CDMA major Reliance has brought a new wave of declining rates in the sector. Aircel also made its foray into the mainstream GSM space with the launch of operations in Delhi and Mumbai.

Source

[Top]
TN farm yard, BSNL sign pact
Infraline.com
  • Tamil Nadu Foodgrains Marketing Yard Ltd has signed a memorandum of understanding with Bharat Sanchar Nigam Ltd for providing agri-business communication services to farmers, foodgrains processors, traders and the consuming public. TFMY is being established to provide better services in processing, upgradation of quality of consumer products and enable farmers get remunerative prices besides drawing attention to better agronomic practices. 

  • To carry forward the message to n ook and corners of the country and abroad, a communication network was felt a necessity, a TFMY press release said. Under the agreement, the BSNL will be establishing a telephone exchange at the yard and would provide services such as telephony, broadband Internet, mobile, wi-fi connectivity etc. The MoU was signed by Mr S. Rethinavelu, Chairman and Managing Director, TFMY, and Mr V.K. Sanjeevi, General Manager, BSNL, Madurai.

Source

[Top]

Cellular Services

Virgin targets 10percent of fresh cell subscriptions
  • Virgin Mobile, the Virgin group's 50:50 joint venture with Tata Teleservices (TTSL), is targeting 10% share of incremental cellular subscribers in the next three years. If the current rate of around 15 million monthly additions continue, Virgin is looking at a base of over 54 million users by FY12. “We are looking at atleast 10% share of incremental market in the next three years through our differentiated offerings,” Virgin Mobile CEO MA Madhusudan said at a press conference in Mumbai on Tuesday (April 28). Virgin Mobile rolled out its branded services in March last year in India. However, its subscriber base or revenues are not known as they are accounted for in the books of TTSL. Mr Madhusudan declined to divulge numbers. Virgin was the first to introduce the concept of 'get paid for receiving calls' in India, where customers are credited with 10 paise for every call they receive. "That number is now down to 5 paise per call after regulatory changes. The benefits to users will continue as we share what we get," he said, ruling out any further reductions. 

  • Mr Madhusudan pointed out that Virgin was ahead of the industry in terms of non-voice revenues. "While around 8% of the industry's revenues come from non-voice services (excluding SMS), the number for us is 10% and is higher than industry average," he added. Virgin also unveiled a music phone, called vJazz, which allows free unlimited download of music tracks for one year. Prized at Rs 4,250, the handset has a 1.3 megapixel camera, 1,000 SMS and phonebook storage space, besides other features. The phone comes with a 1 GB SSD card, allowing ample memory space to save or listen to music. 

Source

[Top]
GSM mobile PCO unveiled
  • Bharat Sanchar Nigam Ltd (BSNL) has introduced GSM (global system for mobile communication) public call office (PCO) for customers in the Tuticorin Telecom District. According to Mr N.R. Natarajan, General Manager, BSNL, Tuticorin, the customers will need to buy a sim card for use by applying with photo and address proof from the authorised outlets of BSNL. Call conferencing facility is also available in the mobile PCO. The cost of the card is Rs 221 with a free talk time worth Rs 50. Further recharge cards are available for Rs 5,515 with a duration of 30 day validity and the customer can talk up to Rs 9,502. The call charges and duration will vary according to destinations, he added.

Source

[Top]

General

Spectrum auction to pave way for 3G-WiMax combo package
Infraline.com
  • Indian telecom service operators are expected to offer a combination of 3G and WiMax (highspeed wirelessbroadband access) once spectrum auction for the two takes place post-elections when the new government assumes office. The combination of the two technology will gain popularity in the present conditions for cost reasons where funds are hard to come by apart from the intrinsic technological value of the two. 

  • CS Rao, chairman, WiMax Forum, India chapter said that operators are likely to go for 3G spectrum for voice services because the 2G spectrum availability is not much and higher spectrum is needed to support subscribers for voice usage. For data services like video streaming, WiMax will be used. 

  • Some vendors have already started manufacturing handsets, which support both 3G for voice and WiMax for data. Another reason will be cost, Rao said. The cost of deploying WiMax base station is much lower (about one-tenth) of deploying 3G network. The cost of setting a WiMax BTS is around $14,000 as against $35,000 for setting up 3G base stations. WiMax and 3G spectrum auctions are expected to held once the new government resolves issues with regard to reserve price. 

  • Rao said that he expects the auction to take place within two months of the new government coming to power. “Broadband penetration is the need of the hour... even the political parties have been giving a lot of weightage to broadband. Notwithstanding which political party comes to power they are likely to settle the issue within two months,” Rao said. Once WiMax spectrum auction takes place WiMax BTS can be deployed by operators within 90-120 days, whereas 3G network will take not less than six months apart from the higher cost. WiMax or the Worldwide Interoperability for Microwave Access, is a telecommunications technology that provides wireless transmission of data at a speed of up to 3 mbps without the need for cables and even while on the move. The technology will give an impetus to the penetration of broadband in the country and give immense push to the various e-governance programmes. India has about 6 million broadband connections now and is adding around 1 million subscribers per year. However, the government had set a target of 20 million users by 2010. 

Source

[Top]
SEBI wants Bharti to clarify on stake hike
Infraline.com
  • The Securities and Exchange Board of India has sought clarifications from Bharti Group on whether the company has violated its norms by increasing promoter’s stake in Bharti Airtel from 60.91 per cent to 67.03 per cent without announcing an open offer. According to SEBI regulations, promoter group companies who together hold more than 55 per cent stake in an entity, have to go for a public offer if they acquire more than 5 per cent stake in a single financial year.SEBI has taken into account equity shares held by Bharti Telecom Ltd, Pastel Ltd and Indian Continental Investment Ltd in calculating the promoter group’s stake. When contacted, Bharti spokesperson said ICIL, a Bharti Group company, acquired 4.99 per cent in Bharti Airtel in FY 2007-08 and 1.28 per cent in FY 2008-09.“Both these transactions have been undertaken during two different financial years and are well within the creeping acquisition limit of 5 per cent in each financial year as permitted under the takeover regulations. Therefore, there is no question of breach of any takeover regulation. We have also filed the requisite declarations to the stock exchanges on all these transactions in time.” “While Pastel Ltd (owned by the Government of Singapore) is classified as a “deemed promoter”, it is not ‘a person acting in concert’ with the Bharti Group. Therefore, the shareholding of Pastel and Bharti Group can not be aggregated while determining the creeping acquisition limit,” the spokesperson said.

Source

[Top]
Loop, Essar email IDs are same: govt
  • The ministry of corporate affairs (MCA) has found fresh evidence to point out that the Essar Group may have substantial interest in Loop Telecom. For instance, the e-mail IDs registered with the MCA of Essar Teleholdings Ltd is the same as that of Santa Trading, BPL Communications Ltd and Santa Securities Pvt Ltd as well as Loop Telecom Pvt Ltd. 

  • In its communication, MCA had said that the Essar Group does not hold more than 9.9% stake indirectly in Loop Telecom, but has provided funding to the tune of Rs 1,592 crore to the new operator through a host of instruments including non-convertible debentures. As per the existing telecom licensing rules, Essar Group currently owns close to 33% stake in its joint venture with Vodafone and, therefore, cannot have more than 10% stake in Loop Telecom which received licence to operate in 22 cities across the country. 

  • “It appears that through the funding of Santa Trading Pvt Ltd by the Essar Group, equity has been provided to BPL Communicationsm, which owns 48% of Loop Telecom,” the MCA told the DoT. MCA also added that Loop Telecom is owned by Santa Trading Pvt Ltd. This is owned by Ruias sister Kiran Khaitan, who owns BPL Communications and BPL Mobile Communications. Though the Essar group does not have any direct equity in Santa Trading, it, however, holds 9.99% in Loop Telecom.

Source

[Top]
 
  
>> | Transport ( 5 News Items)

Roads

Pinjore-Nalagarh highway to be four laned
  • The ministry of road transport and highways has approved the four laning of Pinjore-Nalagarh highway and has asked the Himachal Pradesh government to prepare a feasibility report on the same. The ministry clarified about the approval in a reply filed in the Punjab and Haryana High Court in relation to a Public Interest Litigation (PIL) filed by the Baddi Barotiwala Nalagarh Industries Association (BBNIA) along with Laghu Udyog Bharati. 

  • The association had filed a writ petition in the high court peeved over the indifferent attitude of the Haryana government and ministry of road transport and highways over repair of National Highway No 21A, especially the portion from Pinjore to Baddi. The writ was treated as PIL in its first hearing held on March 18. The latest hearing was held on April 24 in which the reply was filed. 

  • In its petition, the association had urged the high court to give directions to the officials concerned in the Haryana government as well as of the ministry of road transport for immediate repair of road portion from Pinjore to Marranwala to Baddi without any delay. The association also requested the high court to give directions for the widening of road to four/six lane as per volume of traffic. The road transport ministry also stated that around Rs 4.86 crore have been released to the Haryana government for repairing this stretch. 

  • The four laning will take place in two phases. The Haryana Public Works Department (National highways) and Himachal government have been asked to complete the repair work soon. Deepak Bhandari, advisor of BBNIA, said that the association approached the high court about a month ago after making endless efforts to take up the matter with the Haryana PWD (NH) department. “Since, the transport ministry has approved the four laning process, work is expected to be complete soon. The Himachal government is likely to prepare the feasibility report in three-four months and by then the repair work is expected to be complete.” It is pertinent to note that there was no pucca road connecting Pinjore with the Baddi industrial belt. Despite industry representatives holding several protests and meetings with the government officials, no sign of progress could be seen on this link since last few years. Now, the repair work on the stretch is in progress. The stretch from Pinjore to 2.2 km ahead is being repaired and about 75% of the work is complete. From 2.2 km to 11.5 km, the tenders will soon be allotted for its widening and relaying. And from 11.5 km to 17.5 km, the work has been allotted and will be complete by June. The total cost on repair of this stretch comes to around Rs 15 crore.

Source

[Top]

Shipping

Bangladesh may allow India to use its new deep sea port off Chittagong for exports from its north eastern states
  • Bangladesh may allow India to use its new deep sea port off Chittagong for exports from its north eastern states. The new port, the first phase of which is expected to be completed by 2016, can be used as a regional transit hub for India’s northeastern states, Nepal and Bhutan. Top officials said they expected Bangladesh to ask for better transit through Indian territory to Nepal, Bhutan and perhaps even China for letting India use its port.India has been keen on using Bangla ports for exports from its land-locked northeastern states. Chittagong used to be the preferred port till 1965. But a war between India and Pakistan stopped commerce through that route. Successive Bangla governments have ignored the demand for reopening Chittagong port for Indian use. Bangla strategists had earlier said the route could breach the country’s security. Irked by Bangladesh’s attitude in the past over opening up Chittagong port, India had started talks with Myanmar to develop Sitwe port in the Arakan province as an alternative gateway.Bangladesh, whose Chittagong port is increasingly getting overloaded, now plans to build a modern port with large container facilities which it could offer as a regional trade hub. Pacific Consultant International (PCI) of Japan has prepared a feasibility study for the projected $1.2-billion deep sea port which will be built off Sonadia island, 60 km from the existing Chittagong port. 

  • The port, to be built in three phases, will have six harbours and a capacity to handle 100 million tonnes of cargo. If transit facilities are allowed and the port connects to mainland India, it could rival the deep sea port project India is planning in Bengal. At present, Sri Lanka’s Colombo port is the favoured port for exports from south India because of its modern facilities. As a result, about 60 per cent of the container traffic to and from south India is trans-shipped from Colombo and not from Chennai. 

Source

[Top]
Concor steps up services to Pipavav on increased traffic
Infraline.com
  • Container Corporation of India (Concor) has stepped up the number of its services to Port Pipavav in Gujarat thanks to a spurt in traffic volume. Mr Yash Vardhan, Director (International Marketing & Operation), said over the phone from New Delhi that the number of services between different inland container depots (ICDs) in the hinterland (northern and western regions) and the port was now close to two rakes a day, each direction, on an average.

  • The ICDs in the hinterland now connected to the port are located in Ahmedabad, Dadri, Jaipur, Jodhpur, Tughlakabad and Ludhiana. “Besides, we run regular reefer trains from Dadri,” said Mr Vardhan, pointing out that six reefer trains had moved so far from Dadri to Port Pipavav and the seventh one was currently loading.Earlier, i.e. till about a couple of months ago, the container train services to and from Port Pipavav were few and far between (with one or two trains a month) and that too with no fixed departures. “We’ve been responsive to the needs of the trade by stepping up the number of services and, depending on the cargo support, we will have no problems in offering more services,” Mr Vardhan made it clear.While the scheduled trains are now single stacked, there is a possibility of moving double stacked trains in a not too distant future, particularly between Jaipur/Jodhpur and the port. It might be noted that Pipavav Rail Corporation Ltd, a joint venture between Indian Railways and Gujarat Pipavav Port Ltd, has constructed a 271-km long broad gauge line between Surendranagar Junction on Western Railway and the port via Rijula. “PRCL maintains the line, while we offer the rolling stock,” Mr Vardhan added.

Source

[Top]
Strike at Kochi Port; Navy’s help sought for ship movement
  • Kochi Port has sought the assistance of the Indian Navy for smooth vessel movements after a strike resorted to by workers against the implementation of new manning scale. With the introduction of the National Industrial Tribunal Award, the marine crew as well as workers in the cargo handling section resisted implementing the award, which had resulted in disruption of marine operations. The new manning scale has been implemented in other operational areas such as traffic, mechanical and electrical departments where work is going on smoothly.

  • The port officials clarified that the reduction of manning scale will significantly resolve the shortage of personnel in various categories as well as reduce cargo handling cost in major ports, which will boost Exim trade. There will be no loss of employment potential for the workers due to the implementation of the award, the officials said. A senior port official said that the Naval officials are assisting the Port’s masters and engineers to operate the tugs for mooring operations and they were able to bring in more than five vessels and take out four vessels on Tuesday (April 28).The port had carried out around 10 movements on Monday (April 27) with the help of the Navy since the strike began. The officials also pointed out that the operations in the single point mooring were not affected as BPCL-KRL is using hired tugs for mooring operations. According to IGTPL officials, the strike has not affected the container terminal operations as the company managed to carry out cargo movements inside the terminal with 10 hired trailers.

  • Meanwhile, the Thuramugha Samrakshana Samithy, a forum of trade unions, alleged that the port authorities implemented the tribunal settlement unilaterally while other major ports put implementation on hold. The award, which had not been implemented for the last three years, had lost its legal validity, they said. If implemented, it would result in about 500 people directly employed by Kochi Port losing their jobs, the union forum alleged.

  • The step to slash jobs at the ports has been taken without a scientific assessment of the working of the ports, they added. The trade unions appealed for the withdrawal of the orders and for renewed discussions on the issues involved. They also warned that the trade unions would be forced to draw up strong protest action at the regional and national levels against the implementation of the award.

Source

[Top]

Airports

Govt steps up surveillance at international airports
  • To prevent the entry and spread of swine flu virus in the country, the Government has put in place a series of measures including screening air travellers arriving at nine major international airports and setting up quarantine areas at these airports. Official sources said that from Wednesday (April 29), there will be enhanced surveillance of international passengers arriving at Delhi, Mumbai, Hyderabad, Bangalore, Chennai, Goa, Kochi, Kolkata and Jaipur.

  • “This is being done to prevent the entry of passengers who may be carrying the virus. If there is a need, screening quarantine areas will be identified at the airports to segregate such passengers,” a senior Government official said. Passengers arriving from affected countries including the US, Mexico, Canada and Spain could come in for closer scrutiny.The Health Ministry is also working on a form to be given to all international passengers arriving in the country seeking details of whether they have been in a swine flu affected area in the recent past. “The forms, which will be on lines of the yellow fever forms which used to be distributed earlier, should be ready by Wednesday (April 29). The Ministry of Civil Aviation will be responsible for distributing these to airlines flying into the country,” an official said.Meanwhile, Mumbai International Airport Ltd (MIAL) will be providing infrastructural support at the airport to Airport Health Officials (AHO) who will begin screening incoming passengers from Wednesday (April 29) midnight. The inbound passengers from swine influenza affected nations will be screened for symptoms of the viral before they enter the immigration area, said a MIAL spokesperson.

  • MIAL will be setting up counters apart from providing a few rest rooms and an ambulance at the airport to assist AHOs in their check-up procedures. Despite the rapid spread of the virus, it was still too early to gauge its real impact on the industry, leading travel agents felt. According to Mr Ashwini Kakkar, Executive Vice-President, Mercury Travels, customers travelling in the next 10-15 days to the affected areas have been enquiring on what they should be doing before visiting those countries.

  • “However, we have not been able to conclusively suggest anything to them because there is very little known about the infection at the moment. There should be more clarity on the situation by next week or so,” he said. Mr Kakkar added that if the fear about the infection continues, the travel business could be impacted. The acting President, Travel Agents Fraternity of India, Mr Pradip Lulla said that so far there have been no cancellations. Thomas Cook’s India office also said it has not witnessed any major change in customers’ travel plans, as of now.

Source

[Top]
 
 ABOUT INFRALINE.COM DAILY NEWS SERVICES  

INFRALINE DAILY NEWSLETTERS

  • Infraline "Comprehensive Daily Newsletter" is available to the paid users only. Any unauthorized distribution may lead to immediate termination of subscription. Please see below for link to Product, Services and Subscription details.

  •  The "Headlines newsletter" service is provided FREE to qualified professionals of the Infrastructure industry.  This e-mail summary may be redistributed provided it is kept in its entirety. Non registered members may sign up for the Free Daily Headlines Newsletter athttp://www.infraline.com/subscribe_newsletter.asp.

  • If you don't want to receive the E mail Newsletter, thenclick here.

INFRALINE DATA CENTER

  • Indian Power Sector Database (http://power.infraline.com): Extensive information on Regulatory framework, Reforms and Policies, Acts, Notifications, Demand-supply Projections, Players, Comprehensive information on Thermal, Hydro and Captive power etc. Please see below for link to Product, Services and Subscription details.

  • Indian Oil & Gas Sector Database (http://oilandgas.infraline.com): Comprehensive Information on Upstream, Midstream and Downstream, ongoing projects, Investment opportunities, Policy, latest prices of petroleum products etc. Please see below for link to Product, Services and Subscription details.

  • Indian Coal Sector Database " &_ (http://Telecom.infraline.com):In depth information on Regulatory framework, financing, paging market, equipment sector, service sector, Public Mobile Radio Trunking Service, Satellite Communications, Internet, Market Analysis Research reports and Value-Added services.

  • Infraline also provides to its users Cutomised Information Bulletins to keep them abreast of the latest developments in the segments of their core interest. You can send us a mail atcib@infraline.com with your information preferences and we shall revert to you within 24hrs with the Information required by you.

PRESS RELEASES
Submit press releases and other news to
pr@infraline.com 

SPONSORSHIP AND ADVERTISING
For sponsorship or advertising info pleaseclick here or send us a request at
advertising@infraline.com

CLIENT LIST
Infraline's Illustrative Client is available athttp://www.infraline.com/clients/newclients.htm

PRODUCTS, SERVICES AND SUBSCRIPTION DETAILS
For subscription details, please visithttp://www.infraline.com/DetailedProposalForSubscription.doc

Infraline.com is committed to provide to its users the latest, authentic, and relevant information on real time basis.

For any query /suggestion, please contact us at:

India.
Tel : +91-11-6625 0000
Fax: +91-11-6625 0099
Email: info@infraline.com 
Mobile: +91-9810806011

For subscription details, please visithttp://www.infraline.com/DetailedProposalForSubscription.doc

 
 Back to the top